Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Rutgers, State Univ. of NJ |
---|---|
Assessment Year | 1989 |
Principal Product | WALL COVERING, SHADES |
NAICS | n/a |
SIC | 3081 - Unsupported Plastics Film & Sheet |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 82,500 Thousand Feet |
Production Hrs. Annual | 5,390 |
Location (State) | NJ |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $172,923 | 2,080,891 | kWh | $0.08 |
Natural Gas | $44,147 | 12,721 | MMBtu | $3.47 |
Fuel Oil #4 | $24,343 | 6,487 | MMBtu | $3.75 |
TOTAL ENERGY COSTS | $241,413 | |||
RECOMMENDED SAVINGS* | $21,171 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,795 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #4 | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #4 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,192 Cost: $159 |
$1,192 | 14,361 | - | - | - | - | - | - |
$1,192 14,361 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,566 Cost: - |
$6,566 | 79,132 | - | - | - | - | - | - |
$6,566 79,132 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,084 Cost: - |
$1,205 | 31,946 | - | - | - | - | $(-121) | - |
$1,205 31,946 kWh |
- - MMBtu |
- - MMBtu |
$(-121) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4312 IMPROVE LUBRICATION PRACTICES |
Savings: $1,897 Cost: $800 |
$1,897 | 22,860 | - | - | - | - | - | - |
$1,897 22,860 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,240 Cost: - |
$1,240 | 14,947 | - | - | - | - | - | - |
$1,240 14,947 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $5,711 Cost: $8,300 |
- | - | $3,498 | 1,008 | $2,213 | 590 | - | - |
- - kWh |
$3,498 1,008 MMBtu |
$2,213 590 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2444 USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS |
Savings: $3,481 Cost: $9,000 |
- | - | $1,385 | 399 | $2,096 | 559 | - | - |
- - kWh |
$1,385 399 MMBtu |
$2,096 559 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $21,171 Cost: $18,259 |
$12,100 | 163,246 | $4,883 | 1,407 | $4,309 | 1,149 | $(-121) | - | $12,100 163,246 kWh |
$4,883 1,407 MMBtu |
$4,309 1,149 MMBtu |
$(-121) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,795 Cost: $8,300 |
$1,205 | 31,946 | $3,498 | 1,008 | $2,213 | 590 | $(-121) | - | $1,205 31,946 kWh |
$3,498 1,008 MMBtu |
$2,213 590 MMBtu |
$(-121) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #4 | Administrative Changes | Electricity Usage | Natural Gas | Fuel Oil #4 | Administrative Changes |