IAC Assessment: RU0063
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: RU0063
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Rutgers, State Univ. of NJ
Assessment Year 1989
Principal Product METAL CASKETS
NAICS n/a
SIC 3995 - Burial Caskets
Sales $10,000,000-$50,000,000
# of Employees 275
Plant Area (Sq.Ft.) 0
Annual Production 100,000 Pieces
Production Hrs. Annual 2,000
Location (State) PA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $119,760 1,449,004 kWh $0.08
Natural Gas $46,195 15,873 MMBtu $2.91
TOTAL ENERGY COSTS $165,955
RECOMMENDED SAVINGS* $25,755 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $19,730
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$6,103
Cost:
-
$6,103 73,857 - - $6,103
73,857
kWh
-
-
MMBtu
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$6,025
Cost:
-
$6,025 72,978 - - $6,025
72,978
kWh
-
-
MMBtu
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,741
Cost:
$6,626
$3,741 45,135 - - $3,741
45,135
kWh
-
-
MMBtu
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,318
Cost:
-
$4,318 52,169 - - $4,318
52,169
kWh
-
-
MMBtu
05: 2.7441 REPLACE BROKEN WINDOWS AND/OR WINDOW SASH Savings:
$3,381
Cost:
-
- - $3,381 1,166 -
-
kWh
$3,381
1,166
MMBtu
06: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$989
Cost:
$2,000
- - $989 341 -
-
kWh
$989
341
MMBtu
07: 2.2515 USE OPTIMUM THICKNESS INSULATION Savings:
$856
Cost:
$400
- - $856 295 -
-
kWh
$856
295
MMBtu
08: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$342
Cost:
$81
- - $342 118 -
-
kWh
$342
118
MMBtu
TOTAL RECOMMENDED Savings:
$25,755
Cost:
$9,107
$20,187 244,139 $5,568 1,920 $20,187
244,139
kWh
$5,568
1,920
MMBtu
TOTAL IMPLEMENTED Savings:
$19,730
Cost:
$9,107
$14,162 171,161 $5,568 1,920 $14,162
171,161
kWh
$5,568
1,920
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas