IAC Assessment: RU0106
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: RU0106
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Rutgers, State Univ. of NJ
Assessment Year 1991
Principal Product PRINTING & ENGRAVING
NAICS n/a
SIC 2759 - Commercial Printing, Nec
Sales $10,000,000-$50,000,000
# of Employees 384
Plant Area (Sq.Ft.) 0
Annual Production 130,000,000 Pieces
Production Hrs. Annual 0
Location (State) NJ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $242,149 2,616,061 kWh $0.09
Natural Gas $26,875 4,334 MMBtu $6.20
TOTAL ENERGY COSTS $269,024
RECOMMENDED SAVINGS* $17,682 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,682
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$798
Cost:
-
$798 8,499 - - $798
8,499
kWh
-
-
MMBtu
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$648
Cost:
-
$648 7,034 - - $648
7,034
kWh
-
-
MMBtu
03: 2.4312 IMPROVE LUBRICATION PRACTICES Savings:
$507
Cost:
$800
$507 5,569 - - $507
5,569
kWh
-
-
MMBtu
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$645
Cost:
$500
- - $645 104 -
-
kWh
$645
104
MMBtu
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$5,924
Cost:
-
$8,082 86,753 $(-2,158) (-348) $8,082
86,753
kWh
$(-2,158)
(-348)
MMBtu
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$9,160
Cost:
$218
$9,160 98,769 - - $9,160
98,769
kWh
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$17,682
Cost:
$1,518
$19,195 206,624 $(-1,513) (-244) $19,195
206,624
kWh
$(-1,513)
(-244)
MMBtu
TOTAL IMPLEMENTED Savings:
$17,682
Cost:
$1,518
$19,195 206,624 $(-1,513) (-244) $19,195
206,624
kWh
$(-1,513)
(-244)
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas