Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 1991 |
Principal Product | MEDICAL SUPPLIES |
NAICS | n/a |
SIC | 3842 - Surgical Appliances And Supplies |
Sales | $10,000,000-$50,000,000 |
# of Employees | 149 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 10,598 Pieces |
Production Hrs. Annual | 2,250 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $169,191 | 1,953,986 | kWh | $0.09 |
Natural Gas | $32,680 | 5,053 | MMBtu | $6.47 |
TOTAL ENERGY COSTS | $201,871 | |||
RECOMMENDED SAVINGS* | $14,131 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,131 |
#|Description |
Savings Cost |
Status | Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $147 Cost: $315 |
$147 | 1,758 | - | - |
$147 1,758 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $467 Cost: $435 |
$467 | 5,275 | - | - |
$467 5,275 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7123 KEEP LAMPS AND REFLECTORS CLEAN |
Savings: $3,477 Cost: - |
$3,160 | 26,964 | $317 | - |
$3,160 26,964 kWh |
$317 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7123 KEEP LAMPS AND REFLECTORS CLEAN |
Savings: $821 Cost: - |
$749 | 8,499 | $72 | - |
$749 8,499 kWh |
$72 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $5,746 Cost: $600 |
$5,746 | 66,530 | - | - |
$5,746 66,530 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $3,473 Cost: $6,900 |
$3,473 | 36,049 | - | - |
$3,473 36,049 kWh |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $14,131 Cost: $8,250 |
$13,742 | 145,075 | $389 | - | $13,742 145,075 kWh |
$389 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,131 Cost: $8,250 |
$13,742 | 145,075 | $389 | - | $13,742 145,075 kWh |
$389 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Administrative Changes | Electricity Usage | Administrative Changes |