IAC Assessment: SD0150
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0150
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 1996
Principal Product Plated Metals and Plastic Products
NAICS n/a
SIC 3471 - Plating And Polishing
Sales $10,000,000-$50,000,000
# of Employees 300
Plant Area (Sq.Ft.) 163,651
Annual Production 1,000,000 Pieces
Production Hrs. Annual 3,960
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $725,987 11,097,304 kWh $0.07
Electricity Demand $211,349 30,274 kW-months/year $6.98
Natural Gas $247,501 72,012 MMBtu $3.44
TOTAL ENERGY COSTS $1,227,193
RECOMMENDED SAVINGS* $82,518 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $75,150
#|Description Savings
Cost
Status Electricity Usage Natural Gas Water Disposal Solid Waste (haz) Electricity Usage Natural Gas Water Disposal Solid Waste (haz)
$ kWh $ MMBtu $ Tgal $ lb
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$18,102
Cost:
$21,570
$18,102 199,590 - - - - - - $18,102
199,590
kWh
-
-
MMBtu
-
-
Tgal
-
-
lb
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,242
Cost:
$3,920
$2,242 31,653 - - - - - - $2,242
31,653
kWh
-
-
MMBtu
-
-
Tgal
-
-
lb
03: 2.1242 MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT Savings:
$10,042
Cost:
$4,160
- - $10,042 2,953 - - - - -
-
kWh
$10,042
2,953
MMBtu
-
-
Tgal
-
-
lb
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$2,408
Cost:
$3,077
- - $2,408 708 - - - - -
-
kWh
$2,408
708
MMBtu
-
-
Tgal
-
-
lb
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$7,368
Cost:
$5,825
$7,368 75,615 - - - - - - $7,368
75,615
kWh
-
-
MMBtu
-
-
Tgal
-
-
lb
06: 3.4151 MINIMIZE WATER USAGE Savings:
$7,565
Cost:
$3,410
- - - - $7,565 - - - -
-
kWh
-
-
MMBtu
$7,565
-
Tgal
-
-
lb
07: 3.6114 USE PRECIPITATING AGENTS IN WASTE WATER TREATMENT THAT PRODUCE THE LEAST QUANTITY OF WASTE Savings:
$34,791
Cost:
$5,000
- - - - - - $34,791 - -
-
kWh
-
-
MMBtu
-
-
Tgal
$34,791
-
lb
TOTAL RECOMMENDED Savings:
$82,518
Cost:
$46,962
$27,712 306,858 $12,450 3,661 $7,565 - $34,791 - $27,712
306,858
kWh
$12,450
3,661
MMBtu
$7,565
-
Tgal
$34,791
-
lb
TOTAL IMPLEMENTED Savings:
$75,150
Cost:
$41,137
$20,344 231,243 $12,450 3,661 $7,565 - $34,791 - $20,344
231,243
kWh
$12,450
3,661
MMBtu
$7,565
-
Tgal
$34,791
-
lb
Savings
Cost
$ kWh $ MMBtu $ Tgal $ lb
Electricity Usage Natural Gas Water Disposal Solid Waste (haz) Electricity Usage Natural Gas Water Disposal Solid Waste (haz)