Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 1997 |
Principal Product | Computer Printers |
NAICS | n/a |
SIC | 3577 - Computer Peripheral Equipment, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 90,000 |
Annual Production | 15,600 Pieces |
Production Hrs. Annual | 5,750 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $284,252 | 3,951,348 | kWh | $0.07 |
Electricity Demand | $72,090 | 9,003 | kW-months/year | $8.01 |
Natural Gas | $3,124 | 501 | MMBtu | $6.24 |
TOTAL ENERGY COSTS | $359,466 | |||
RECOMMENDED SAVINGS* | $88,416 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $46,655 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Other Liquid (haz) | Administrative Changes | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Other Liquid (haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | gal | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2614 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING |
Savings: $20,154 Cost: $3,300 |
$20,154 | 288,394 | - | - | - | - | - | - | - | - |
$20,154 288,394 kWh |
- - kW-months/year |
- - gal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $9,714 Cost: $11,700 |
$8,423 | 117,233 | $1,291 | 161 | - | - | - | - | - | - |
$8,423 117,233 kWh |
$1,291 161 kW-months/year |
- - gal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,459 Cost: - |
$1,259 | 17,585 | $200 | 25 | - | - | - | - | - | - |
$1,259 17,585 kWh |
$200 25 kW-months/year |
- - gal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $941 Cost: $469 |
$770 | 10,551 | $171 | 21 | - | - | - | - | - | - |
$770 10,551 kWh |
$171 21 kW-months/year |
- - gal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $1,809 Cost: $4,110 |
$1,085 | 14,947 | $724 | 90 | - | - | - | - | - | - |
$1,085 14,947 kWh |
$724 90 kW-months/year |
- - gal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,082 Cost: $1,845 |
$129 | 37,808 | $953 | 119 | - | - | - | - | - | - |
$129 37,808 kWh |
$953 119 kW-months/year |
- - gal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.8224 CONVERT TO LESS TOXIC HYDROCARBON CLEANERS |
Savings: $1,894 Cost: - |
- | - | - | - | - | - | $1,894 | 700 | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$1,894 700 gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.3128 UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS |
Savings: $11,496 Cost: $3,480 |
- | - | - | - | - | - | - | - | $11,496 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - gal |
$11,496 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.1171 CHANGE PRODUCT SPECS |
Savings: $39,867 Cost: - |
- | - | - | - | $39,867 | 6,500 | - | - | - | - |
- - kWh |
- - kW-months/year |
$39,867 6,500 gal |
- - gal |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $88,416 Cost: $24,904 |
$31,820 | 486,518 | $3,339 | 416 | $39,867 | 6,500 | $1,894 | 700 | $11,496 | - | $31,820 486,518 kWh |
$3,339 416 kW-months/year |
$39,867 6,500 gal |
$1,894 700 gal |
$11,496 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $46,655 Cost: $24,904 |
$31,820 | 486,518 | $3,339 | 416 | - | - | - | - | $11,496 | - | $31,820 486,518 kWh |
$3,339 416 kW-months/year |
- - gal |
- - gal |
$11,496 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | gal | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Other Liquid (haz) | Administrative Changes | Electricity Usage | Electricity Demand | Other Liquid (non-haz) | Other Liquid (haz) | Administrative Changes |