Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 1997 |
Principal Product | Heat Transfer Products |
NAICS | n/a |
SIC | 3585 - Refrigeration And Heating Equipment |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 75,000 |
Annual Production | 42,000 Pieces |
Production Hrs. Annual | 4,250 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $67,379 | 950,762 | kWh | $0.07 |
Electricity Demand | $21,338 | 2,571 | kW-months/year | $8.30 |
Natural Gas | $6,624 | 1,091 | MMBtu | $6.07 |
TOTAL ENERGY COSTS | $95,341 | |||
RECOMMENDED SAVINGS* | $116,978 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $57,278 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Other Liquid (haz) | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,363 Cost: $2,363 |
$1,691 | 23,740 | $672 | 81 | - | - | - | - | - | - |
$1,691 23,740 kWh |
$672 81 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,392 Cost: - |
$1,052 | 14,947 | $340 | 41 | - | - | - | - | - | - |
$1,052 14,947 kWh |
$340 41 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,773 Cost: $6,741 |
$1,366 | 19,343 | $407 | 49 | - | - | - | - | - | - |
$1,366 19,343 kWh |
$407 49 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $744 Cost: $1,190 |
$571 | 7,913 | $173 | 21 | - | - | - | - | - | - |
$571 7,913 kWh |
$173 21 kW-months/year |
- - gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $22,100 Cost: $9,000 |
- | - | - | - | - | - | $22,100 | - | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$22,100 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.8224 CONVERT TO LESS TOXIC HYDROCARBON CLEANERS |
Savings: $2,462 Cost: - |
- | - | - | - | $2,462 | 122 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,462 122 gal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.7134 WASH AND REUSE RAGS ON-SITE |
Savings: $1,262 Cost: $1,600 |
- | - | - | - | - | - | - | - | $1,262 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - $ |
$1,262 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.441 INSTALL AUTOMATIC PACKING EQUIPMENT |
Savings: $25,182 Cost: $9,000 |
- | - | - | - | - | - | $25,182 | - | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$25,182 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.511 EXPAND OPERATIONS INTO UNUSED SPACE |
Savings: $22,500 Cost: $49,750 |
- | - | - | - | - | - | $22,500 | - | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$22,500 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.321 OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES |
Savings: $37,200 Cost: $24,000 |
- | - | - | - | - | - | $37,200 | - | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$37,200 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $116,978 Cost: $103,644 |
$4,680 | 65,943 | $1,592 | 192 | $2,462 | 122 | $106,982 | - | $1,262 | - | $4,680 65,943 kWh |
$1,592 192 kW-months/year |
$2,462 122 gal |
$106,982 - $ |
$1,262 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $57,278 Cost: $29,894 |
$4,680 | 65,943 | $1,592 | 192 | $2,462 | 122 | $47,282 | - | $1,262 | - | $4,680 65,943 kWh |
$1,592 192 kW-months/year |
$2,462 122 gal |
$47,282 - $ |
$1,262 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Other Liquid (haz) | Administrative Changes | Ancillary Material Cost |