IAC logo
IAC Assessment: SD0229
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0229
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 1999
Principal Product Latches and hinges
NAICS n/a
SIC 3429 - Hardware, Nec
Sales $10,000,000-$50,000,000
# of Employees 190
Plant Area (Sq.Ft.) 50,000
Annual Production 40,000 Pounds
Production Hrs. Annual 5,125
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $98,094 1,276,084 kWh $0.08
Electricity Demand $39,101 4,397 kW-months/year $8.89
Electricity Fees $727 - $ -
TOTAL ENERGY COSTS $137,922
RECOMMENDED SAVINGS* $139,679 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $11,917
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Administrative Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ gal $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,875
Cost:
$2,988
$4,623 60,082 $1,252 141 - - - - - - $4,623
60,082
kWh
$1,252
141
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$13,528
Cost:
$10,000
$7,075 92,028 $9,815 1,104 $(-3,362) (-449) - - - - $7,075
92,028
kWh
$9,815
1,104
kW-months/year
$(-3,362)
(-449)
MMBtu
-
-
gal
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,665
Cost:
$500
$1,850 24,033 $815 92 - - - - - - $1,850
24,033
kWh
$815
92
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$3,377
Cost:
$120
$2,581 31,360 $796 83 - - - - - - $2,581
31,360
kWh
$796
83
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$13,502
Cost:
$11,000
$7,682 99,941 $9,473 1,066 $(-3,653) (-487) - - - - $7,682
99,941
kWh
$9,473
1,066
kW-months/year
$(-3,653)
(-487)
MMBtu
-
-
gal
-
-
$
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,372
Cost:
$540
- - - - - - $1,372 1,960 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,372
1,960
gal
-
-
$
07: 4.6510 INSTALL BACK-UP EQUIPMENT Savings:
$23,040
Cost:
$15,000
- - - - - - - - $23,040 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$23,040
-
$
08: 4.4450 INSTALL EQUIPMENT TO MOVE PRODUCT Savings:
$76,320
Cost:
$30,000
- - - - - - - - $76,320 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$76,320
-
$
TOTAL RECOMMENDED Savings:
$139,679
Cost:
$70,148
$23,811 307,444 $22,151 2,486 $(-7,015) (-936) $1,372 1,960 $99,360 - $23,811
307,444
kWh
$22,151
2,486
kW-months/year
$(-7,015)
(-936)
MMBtu
$1,372
1,960
gal
$99,360
-
$
TOTAL IMPLEMENTED Savings:
$11,917
Cost:
$3,608
$9,054 115,475 $2,863 316 - - - - - - $9,054
115,475
kWh
$2,863
316
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ $
Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Administrative Changes Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Administrative Changes