IAC Assessment: SD0273
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0273
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2001
Principal Product Aircraft latches
NAICS n/a
SIC 3365 - Aluminum Foundries
Sales $1,000,000-$5,000,000
# of Employees 50
Plant Area (Sq.Ft.) 80,000
Annual Production 50,000 Pounds
Production Hrs. Annual 4,375
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $64,875 770,830 kWh $0.08
Electricity Demand $27,760 3,550 kW-months/year $7.82
Electricity Fees $54,594 - $ -
Natural Gas $30,023 4,049 MMBtu $7.41
TOTAL ENERGY COSTS $179,178
RECOMMENDED SAVINGS* $26,867 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $16,670
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$4,369
Cost:
$2,000
$2,866 34,036 $1,503 192 - - - - - - $2,866
34,036
kWh
$1,503
192
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
02: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS Savings:
$3,094
Cost:
$1,500
$1,827 21,700 $94 12 $1,173 160 - - - - $1,827
21,700
kWh
$94
12
kW-months/year
$1,173
160
MMBtu
-
-
$
-
-
$
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$3,519
Cost:
$2,000
- - - - $3,519 480 - - - - -
-
kWh
-
-
kW-months/year
$3,519
480
MMBtu
-
-
$
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$822
Cost:
$200
$539 6,405 $283 36 - - - - - - $539
6,405
kWh
$283
36
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
05: 2.4321 UPGRADE OBSOLETE EQUIPMENT Savings:
$5,286
Cost:
$15,000
- - - - $5,286 721 - - - - -
-
kWh
-
-
kW-months/year
$5,286
721
MMBtu
-
-
$
-
-
$
06: 2.7145 INSTALL SKYLIGHTS Savings:
$2,734
Cost:
$6,000
$1,569 18,630 $1,165 149 - - - - - - $1,569
18,630
kWh
$1,165
149
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
07: 3.5222 USE SAND FOR OTHER PURPOSES (EG CONSTRUCTION FILL, COVER FOR MUNICIPAL LANDFILLS) Savings:
$3,043
Cost:
$500
- - - - - - - - $3,043 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
$3,043
-
$
08: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS Savings:
$4,000
Cost:
$3,500
- - - - - - $4,000 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$4,000
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$26,867
Cost:
$30,700
$6,801 80,771 $3,045 389 $9,978 1,361 $4,000 - $3,043 - $6,801
80,771
kWh
$3,045
389
kW-months/year
$9,978
1,361
MMBtu
$4,000
-
$
$3,043
-
$
TOTAL IMPLEMENTED Savings:
$16,670
Cost:
$21,200
$539 6,405 $283 36 $8,805 1,201 $4,000 - $3,043 - $539
6,405
kWh
$283
36
kW-months/year
$8,805
1,201
MMBtu
$4,000
-
$
$3,043
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost