Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2001 |
Principal Product | Brass mill rod and shape products |
NAICS | n/a |
SIC | 3351 - Copper Rolling And Drawing |
Sales | $10,000,000-$50,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 320,000 |
Annual Production | 40,000,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $720,008 | 15,981,904 | kWh | $0.05 |
Electricity Demand | $31,122 | 41,786 | kW-months/year | $0.74 |
Electricity Fees | $28,175 | - | $ | - |
Natural Gas | $169,721 | 33,995 | MMBtu | $4.99 |
TOTAL ENERGY COSTS | $949,026 | |||
RECOMMENDED SAVINGS* | $591,362 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $34,478 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $34,478 Cost: $1,400 |
$33,380 | 741,762 | $1,098 | 1,484 | - | - | - | - | - | - | - | - | - | - |
$33,380 741,762 kWh |
$1,098 1,484 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $32,897 Cost: $60,000 |
$32,002 | 709,578 | $895 | 1,209 | - | - | - | - | - | - | - | - | - | - |
$32,002 709,578 kWh |
$895 1,209 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7145 INSTALL SKYLIGHTS |
Savings: $17,602 Cost: $37,000 |
$15,560 | 345,000 | $2,042 | 2,760 | - | - | - | - | - | - | - | - | - | - |
$15,560 345,000 kWh |
$2,042 2,760 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $1,025 Cost: $2,250 |
$972 | 21,560 | $53 | 72 | - | - | - | - | - | - | - | - | - | - |
$972 21,560 kWh |
$53 72 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $21,557 Cost: $45,000 |
$32,472 | 720,000 | $1,776 | 2,400 | $(-12,691) | (-2,649) | - | - | - | - | - | - | - | - |
$32,472 720,000 kWh |
$1,776 2,400 kW-months/year |
$(-12,691) (-2,649) MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $465,613 Cost: $1,000,000 |
$39,293 | 871,250 | $1,820 | 2,460 | - | - | $48,000 | 50,000 | - | - | $376,500 | - | - | - |
$39,293 871,250 kWh |
$1,820 2,460 kW-months/year |
- - MMBtu |
$48,000 50,000 gal |
- - lb |
$376,500 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $4,190 Cost: $15,000 |
- | - | - | - | - | - | - | - | - | - | - | - | $4,190 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
$4,190 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.7198 REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT |
Savings: $14,000 Cost: $5,800 |
- | - | - | - | - | - | - | - | $14,000 | 39,100 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
$14,000 39,100 lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $591,362 Cost: $1,166,450 |
$153,679 | 3,409,150 | $7,684 | 10,385 | $(-12,691) | (-2,649) | $48,000 | 50,000 | $14,000 | 39,100 | $376,500 | - | $4,190 | - | $153,679 3,409,150 kWh |
$7,684 10,385 kW-months/year |
$(-12,691) (-2,649) MMBtu |
$48,000 50,000 gal |
$14,000 39,100 lb |
$376,500 - $ |
$4,190 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $34,478 Cost: $1,400 |
$33,380 | 741,762 | $1,098 | 1,484 | - | - | - | - | - | - | - | - | - | - | $33,380 741,762 kWh |
$1,098 1,484 kW-months/year |
- - MMBtu |
- - gal |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | One-time Revenue or Avoided Cost |