Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2002 |
Principal Product | foam |
NAICS | n/a |
SIC | 3086 - Plastics Foam Products |
Sales | n/a |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 1,200,000 |
Annual Production | 3,000,000 Units |
Production Hrs. Annual | 6,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,560,041 | 12,658,370 | kWh | $0.12 |
Electricity Demand | $450,003 | 33,683 | kW-months/year | $13.36 |
Electricity Fees | $7,679 | - | $ | - |
Natural Gas | $152,369 | 24,769 | MMBtu | $6.15 |
TOTAL ENERGY COSTS | $2,234,728 | |||
RECOMMENDED SAVINGS* | $1,644,128 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $3,096 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3417 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT |
Savings: $1,365,840 Cost: $2,430,000 |
$1,045,200 | 12,000,000 | $320,640 | 24,000 | - | - | - | - | - | - | - | - |
$1,045,200 12,000,000 kWh |
$320,640 24,000 kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7145 INSTALL SKYLIGHTS |
Savings: $57,206 Cost: $2,700 |
$50,954 | 585,000 | $6,252 | 468 | - | - | - | - | - | - | - | - |
$50,954 585,000 kWh |
$6,252 468 kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $27,381 Cost: $11,000 |
$21,930 | 251,775 | $5,451 | 408 | - | - | - | - | - | - | - | - |
$21,930 251,775 kWh |
$5,451 408 kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $6,500 Cost: $11,000 |
$5,331 | 61,273 | $1,169 | 88 | - | - | - | - | - | - | - | - |
$5,331 61,273 kWh |
$1,169 88 kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,096 Cost: $300 |
$3,096 | 35,545 | - | - | - | - | - | - | - | - | - | - |
$3,096 35,545 kWh |
- - kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,066 Cost: $800 |
$1,066 | 12,240 | - | - | - | - | - | - | - | - | - | - |
$1,066 12,240 kWh |
- - kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $91,045 Cost: $65,000 |
$69,669 | 799,868 | $21,376 | 1,600 | - | - | - | - | - | - | - | - |
$69,669 799,868 kWh |
$21,376 1,600 kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $13,200 Cost: $20,000 |
- | - | - | - | - | - | $13,200 | 30 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - gal |
$13,200 30 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $3,600 Cost: $1,500 |
- | - | - | - | $3,600 | 34 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$3,600 34 gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $40,040 Cost: - |
- | - | - | - | - | - | - | - | - | - | $40,040 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
- - $ |
$40,040 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $33,600 Cost: $1,600 |
- | - | - | - | - | - | - | - | $33,600 | - | - | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
$33,600 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $1,554 Cost: - |
- | - | - | - | - | - | - | - | - | - | $1,554 | - |
- - kWh |
- - kW-months/year |
- - gal |
- - lb |
- - $ |
$1,554 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,644,128 Cost: $2,543,900 |
$1,197,246 | 13,745,701 | $354,888 | 26,564 | $3,600 | 34 | $13,200 | 30 | $33,600 | - | $41,594 | - | $1,197,246 13,745,701 kWh |
$354,888 26,564 kW-months/year |
$3,600 34 gal |
$13,200 30 lb |
$33,600 - $ |
$41,594 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $3,096 Cost: $300 |
$3,096 | 35,545 | - | - | - | - | - | - | - | - | - | - | $3,096 35,545 kWh |
- - kW-months/year |
- - gal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | gal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Other Liquid (haz) | Solid Waste (haz) | Administrative Changes | One-time Revenue or Avoided Cost |