Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2003 |
Principal Product | Soft Drinks |
NAICS | 312111 - Soft Drink Manufacturing |
SIC | 2086 - Bottled And Canned Soft Drinks |
Sales | $10,000,000-$50,000,000 |
# of Employees | 95 |
Plant Area (Sq.Ft.) | 79,000 |
Annual Production | 12,000,000 Pieces |
Production Hrs. Annual | 6,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,129,667 | 9,121,283 | kWh | $0.12 |
Electricity Fees | $155,711 | - | $ | - |
Natural Gas | $124,192 | 30,760 | MMBtu | $4.04 |
TOTAL ENERGY COSTS | $1,498,210 | |||
RECOMMENDED SAVINGS* | $86,254 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $29,228 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $33,835 Cost: $30,000 |
- | - | - | - | $33,835 | 8,400 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$33,835 8,400 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,073 Cost: $600 |
$5,765 | 63,004 | $1,308 | 105 | - | - | - | - | - | - | - | - |
$5,765 63,004 kWh |
$1,308 105 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $5,128 Cost: $3,024 |
- | - | - | - | $5,128 | 1,273 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,128 1,273 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT |
Savings: $5,120 Cost: $20,000 |
- | - | - | - | $5,120 | 1,271 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,120 1,271 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,945 Cost: $4,000 |
$4,353 | 47,577 | $592 | 48 | - | - | - | - | - | - | - | - |
$4,353 47,577 kWh |
$592 48 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7145 INSTALL SKYLIGHTS |
Savings: $4,178 Cost: $9,500 |
$2,191 | 23,940 | $1,987 | 160 | - | - | - | - | - | - | - | - |
$2,191 23,940 kWh |
$1,987 160 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER |
Savings: $2,955 Cost: $2,263 |
- | - | - | - | $2,084 | 796 | $871 | 738,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,084 796 MMBtu |
$871 738,000 Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $8,000 Cost: $10,000 |
- | - | - | - | - | - | - | - | - | - | $8,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
$8,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $3,820 Cost: $14,000 |
- | - | - | - | - | - | $3,820 | 5,184,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$3,820 5,184,000 Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $11,200 Cost: $2,500 |
- | - | - | - | - | - | - | - | $11,200 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
$11,200 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $86,254 Cost: $95,887 |
$12,309 | 134,521 | $3,887 | 313 | $46,167 | 11,740 | $4,691 | 5,922,000 | $11,200 | - | $8,000 | - | $12,309 134,521 kWh |
$3,887 313 kW-months/year |
$46,167 11,740 MMBtu |
$4,691 5,922,000 Tgal |
$11,200 - $ |
$8,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $29,228 Cost: $15,363 |
$5,765 | 63,004 | $1,308 | 105 | $2,084 | 796 | $871 | 738,000 | $11,200 | - | $8,000 | - | $5,765 63,004 kWh |
$1,308 105 kW-months/year |
$2,084 796 MMBtu |
$871 738,000 Tgal |
$11,200 - $ |
$8,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Water Disposal | Personnel Changes | Administrative Changes |