Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2004 |
Principal Product | Cardboard Boxes |
NAICS | 322211 - Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653 - Corrugated And Solid Fiber Boxes |
Sales | $10,000,000-$50,000,000 |
# of Employees | 130 |
Plant Area (Sq.Ft.) | 480,000 |
Annual Production | 46,000 Tons |
Production Hrs. Annual | 4,675 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $222,775 | 3,294,420 | kWh | $0.07 |
Electricity Demand | $20,123 | 7,297 | kW-months/year | $2.76 |
Natural Gas | $52,858 | 63,089 | MMBtu | $0.84 |
TOTAL ENERGY COSTS | $295,756 | |||
RECOMMENDED SAVINGS* | $173,758 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,444 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $164,104 Cost: $609,600 |
$215,317 | 3,185,160 | $16,825 | 6,096 | $(-24,170) | (-28,842) | $(-43,868) | - |
$215,317 3,185,160 kWh |
$16,825 6,096 kW-months/year |
$(-24,170) (-28,842) MMBtu |
$(-43,868) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,679 Cost: $475 |
$1,679 | 24,832 | - | - | - | - | - | - |
$1,679 24,832 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $2,765 Cost: $900 |
- | - | - | - | $2,765 | 3,299 | - | - |
- - kWh |
- - kW-months/year |
$2,765 3,299 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT |
Savings: $1,750 Cost: $6,000 |
- | - | - | - | $1,750 | 2,087 | - | - |
- - kWh |
- - kW-months/year |
$1,750 2,087 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7145 INSTALL SKYLIGHTS |
Savings: $3,460 Cost: $7,015 |
$3,460 | 51,182 | - | - | - | - | - | - |
$3,460 51,182 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $173,758 Cost: $623,990 |
$220,456 | 3,261,174 | $16,825 | 6,096 | $(-19,655) | (-23,456) | $(-43,868) | - | $220,456 3,261,174 kWh |
$16,825 6,096 kW-months/year |
$(-19,655) (-23,456) MMBtu |
$(-43,868) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,444 Cost: $1,375 |
$1,679 | 24,832 | - | - | $2,765 | 3,299 | - | - | $1,679 24,832 kWh |
- - kW-months/year |
$2,765 3,299 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes |