Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2004 |
Principal Product | Bricks |
NAICS | 327120 - Clay Building Material and Refractories Manufacturing |
SIC | 3251 - Brick And Structural Clay Tile |
Sales | $10,000,000-$50,000,000 |
# of Employees | 40 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 80,000,000 Pieces |
Production Hrs. Annual | 7,224 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $114,480 | 1,594,732 | kWh | $0.07 |
Electricity Demand | $72,118 | 7,425 | kW-months/year | $9.71 |
Natural Gas | $488,108 | 89,289 | MMBtu | $5.47 |
TOTAL ENERGY COSTS | $674,706 | |||
RECOMMENDED SAVINGS* | $344,943 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $127,079 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $217,864 Cost: $75,000 |
- | - | - | - | $217,864 | 39,858 | - | - |
- - kWh |
- - kW-months/year |
$217,864 39,858 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3415 USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT |
Savings: $80,766 Cost: $255,442 |
$107,765 | 1,502,997 | $25,518 | 2,628 | $(-52,517) | (-9,608) | - | - |
$107,765 1,502,997 kWh |
$25,518 2,628 kW-months/year |
$(-52,517) (-9,608) MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $34,754 Cost: $39,050 |
$28,375 | 395,752 | $6,379 | 657 | - | - | - | - |
$28,375 395,752 kWh |
$6,379 657 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,248 Cost: $14,785 |
$5,918 | 82,541 | $1,330 | 137 | - | - | - | - |
$5,918 82,541 kWh |
$1,330 137 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,257 Cost: $350 |
$1,393 | 20,825 | $864 | 89 | - | - | - | - |
$1,393 20,825 kWh |
$864 89 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $663 Cost: - |
$663 | 9,243 | - | - | - | - | - | - |
$663 9,243 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.8123 PAY UTILITY BILLS ON TIME |
Savings: $1,391 Cost: - |
- | - | - | - | - | - | $1,391 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,391 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $344,943 Cost: $384,627 |
$144,114 | 2,011,358 | $34,091 | 3,511 | $165,347 | 30,250 | $1,391 | - | $144,114 2,011,358 kWh |
$34,091 3,511 kW-months/year |
$165,347 30,250 MMBtu |
$1,391 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $127,079 Cost: $309,627 |
$144,114 | 2,011,358 | $34,091 | 3,511 | $(-52,517) | (-9,608) | $1,391 | - | $144,114 2,011,358 kWh |
$34,091 3,511 kW-months/year |
$(-52,517) (-9,608) MMBtu |
$1,391 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Natural Gas | One-time Revenue or Avoided Cost |