Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2005 |
Principal Product | Construction Nails |
NAICS | 332613 - Spring Manufacturing |
SIC | 3315 - Steel Wire And Related Products |
Sales | $50,000,000-$100,000,000 |
# of Employees | 80 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 48,000 Tons |
Production Hrs. Annual | 6,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $238,778 | 2,920,779 | kWh | $0.08 |
Electricity Demand | $98,608 | 7,148 | kW-months/year | $13.80 |
TOTAL ENERGY COSTS | $337,386 | |||
RECOMMENDED SAVINGS* | $286,721 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $83,605 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4238 DO NOT USE COMPRESSED AIR FOR PERSONAL COOLING |
Savings: $41,074 Cost: $6,300 |
$30,711 | 375,447 | $10,363 | 751 | - | - |
$30,711 375,447 kWh |
$10,363 751 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $16,917 Cost: - |
$16,917 | 206,812 | - | - | - | - |
$16,917 206,812 kWh |
- - kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $14,251 Cost: $3,500 |
$14,251 | 174,221 | - | - | - | - |
$14,251 174,221 kWh |
- - kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $10,614 Cost: $26,000 |
$7,978 | 97,528 | $2,636 | 191 | - | - |
$7,978 97,528 kWh |
$2,636 191 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $749 Cost: $80 |
$560 | 6,848 | $189 | 14 | - | - |
$560 6,848 kWh |
$189 14 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS |
Savings: $194,956 Cost: $92,000 |
$(-1,220) | (-14,920) | $(-6,177) | (-448) | $202,353 | 275,000 |
$(-1,220) (-14,920) kWh |
$(-6,177) (-448) kW-months/year |
$202,353 275,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $8,160 Cost: $18,500 |
- | - | - | - | $8,160 | - |
- - kWh |
- - kW-months/year |
$8,160 - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $286,721 Cost: $146,380 |
$69,197 | 845,936 | $7,011 | 508 | $210,513 | 275,000 | $69,197 845,936 kWh |
$7,011 508 kW-months/year |
$210,513 275,000 lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $83,605 Cost: $35,880 |
$70,417 | 860,856 | $13,188 | 956 | - | - | $70,417 860,856 kWh |
$13,188 956 kW-months/year |
- - lb |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Electricity Usage | Electricity Demand | Solid Waste (non-haz) |