IAC logo
IAC Assessment: SD0398
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0398
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2007
Principal Product Precision Sheet Metal Manufacturing
NAICS 332322 - Sheet Metal Work Manufacturing
SIC 3724 - Aircraft Engines And Engine Parts
Sales $10,000,000-$50,000,000
# of Employees 55
Plant Area (Sq.Ft.) 7,300
Annual Production 30,000 Pieces
Production Hrs. Annual 4,250
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $85,641 913,920 kWh $0.09
Electricity Demand $45,827 3,175 kW-months/year $14.43
Electricity Fees $6,746 - $ -
Natural Gas $32,725 3,467 MMBtu $9.44
TOTAL ENERGY COSTS $170,939
RECOMMENDED SAVINGS* $32,587 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $25,121
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$23,030
Cost:
$45,224
$16,325 174,222 $6,705 465 - - $16,325
174,222
kWh
$6,705
465
kW-months/year
-
-
MMBtu
02: 2.7145 INSTALL SKYLIGHTS Savings:
$4,253
Cost:
$13,615
$3,012 32,140 $1,241 86 - - $3,012
32,140
kWh
$1,241
86
kW-months/year
-
-
MMBtu
03: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS Savings:
$2,091
Cost:
$150
$1,482 15,816 $609 42 - - $1,482
15,816
kWh
$609
42
kW-months/year
-
-
MMBtu
04: 2.2442 PREHEAT COMBUSTION AIR WITH WASTE HEAT Savings:
$1,860
Cost:
$5,101
- - - - $1,860 197 -
-
kWh
-
-
kW-months/year
$1,860
197
MMBtu
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,353
Cost:
$2,193
$1,353 14,439 - - - - $1,353
14,439
kWh
-
-
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$32,587
Cost:
$66,283
$22,172 236,617 $8,555 593 $1,860 197 $22,172
236,617
kWh
$8,555
593
kW-months/year
$1,860
197
MMBtu
TOTAL IMPLEMENTED Savings:
$25,121
Cost:
$45,374
$17,807 190,038 $7,314 507 - - $17,807
190,038
kWh
$7,314
507
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas