IAC Assessment: SD0399
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0399
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2007
Principal Product Stone countertops and interiors
NAICS 327991 - Cut Stone and Stone Product Manufacturing
SIC 3281 - Cut Stone And Stone Products
Sales $10,000,000-$50,000,000
# of Employees 90
Plant Area (Sq.Ft.) 20,000
Annual Production 12,500 Pieces
Production Hrs. Annual 4,250
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $34,970 414,322 kWh $0.08
Electricity Demand $10,305 811 kW-months/year $12.71
Electricity Fees $29,970 - $ -
TOTAL ENERGY COSTS $75,245
RECOMMENDED SAVINGS* $8,476 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,537
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Usage Electricity Demand
$ kWh $ kW-months/year
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,380
Cost:
$6,025
$1,436 17,017 $944 74 $1,436
17,017
kWh
$944
74
kW-months/year
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$2,267
Cost:
$6,700
$2,267 26,856 - - $2,267
26,856
kWh
-
-
kW-months/year
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,543
Cost:
$4,247
$1,543 18,277 - - $1,543
18,277
kWh
-
-
kW-months/year
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,157
Cost:
$5,934
$797 9,440 $360 28 $797
9,440
kWh
$360
28
kW-months/year
05: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$1,129
Cost:
-
$1,129 13,381 - - $1,129
13,381
kWh
-
-
kW-months/year
TOTAL RECOMMENDED Savings:
$8,476
Cost:
$22,906
$7,172 84,971 $1,304 102 $7,172
84,971
kWh
$1,304
102
kW-months/year
TOTAL IMPLEMENTED Savings:
$3,537
Cost:
$11,959
$2,233 26,457 $1,304 102 $2,233
26,457
kWh
$1,304
102
kW-months/year
Savings
Cost
$ kWh $ kW-months/year
Electricity Usage Electricity Demand Electricity Usage Electricity Demand