Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2009 |
Principal Product | AIRCRAFT FASTENERS |
NAICS | 336413 - Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728 - Aircraft Parts And Equipment, Nec |
Sales | <$500,000 |
# of Employees | 160 |
Plant Area (Sq.Ft.) | 75,000 |
Annual Production | 1 Units |
Production Hrs. Annual | 6,426 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $249,130 | 3,075,657 | kWh | $0.08 |
Electricity Demand | $159,339 | 8,522 | kW-months/year | $18.70 |
Electricity Fees | $12,647 | - | $ | - |
Natural Gas | $25,627 | 2,801 | MMBtu | $9.15 |
TOTAL ENERGY COSTS | $446,743 | |||
RECOMMENDED SAVINGS* | $49,124 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $46,359 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $31,588 Cost: - |
- | - | $31,588 | - |
- - kWh |
$31,588 - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $5,480 Cost: - |
- | - | $5,480 | - |
- - kWh |
$5,480 - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $6,840 Cost: $2,200 |
$6,840 | 84,460 | - | - |
$6,840 84,460 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,765 Cost: $2,554 |
$1,903 | 23,499 | $862 | 46 |
$1,903 23,499 kWh |
$862 46 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,451 Cost: $4,146 |
$2,451 | 30,264 | - | - |
$2,451 30,264 kWh |
- - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $49,124 Cost: $8,900 |
$11,194 | 138,223 | $37,930 | 46 | $11,194 138,223 kWh |
$37,930 46 kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $46,359 Cost: $6,346 |
$9,291 | 114,724 | $37,068 | - | $9,291 114,724 kWh |
$37,068 - kW-months/year |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Usage | Electricity Demand |