Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2023 |
Principal Product | Heat Treated Aluminum Alloys |
NAICS | 332811 - Metal Heat Treating |
SIC | 3398 - Metal Heat Treating |
Sales | $5,000,000-$10,000,000 |
# of Employees | 53 |
Plant Area (Sq.Ft.) | 38,000 |
Annual Production | 200,000 Units |
Production Hrs. Annual | 6,732 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $47,525 | 1,166,425 | kWh | $0.04 |
Electricity Demand | $71,563 | 2,673 | kW-months/year | $26.77 |
Electricity Fees | $25,983 | - | $ | - |
Natural Gas | $124,576 | 22,225 | MMBtu | $5.61 |
TOTAL ENERGY COSTS | $269,647 | |||
RECOMMENDED SAVINGS* | $187,547 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $118,921 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $77,202 Cost: $252,463 |
$14,239 | 349,860 | $62,963 | 2,352 | - | - | - | - |
$14,239 349,860 kWh |
$62,963 2,352 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3141 USE BATTERY STORAGE FOR DEMAND CONTROL |
Savings: $57,958 Cost: - |
$(-1,793) | (-44,051) | $59,751 | 2,232 | - | - | - | - |
$(-1,793) (-44,051) kWh |
$59,751 2,232 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,458 Cost: $1,000 |
$307 | 7,544 | $1,151 | 43 | - | - | - | - |
$307 7,544 kWh |
$1,151 43 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $22,128 Cost: $51,000 |
- | - | - | - | $22,128 | 3,944 | - | - |
- - kWh |
- - kW-months/year |
$22,128 3,944 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $10,668 Cost: $37,853 |
$6,983 | 171,579 | $7,791 | 291 | $(-4,106) | (-732) | - | - |
$6,983 171,579 kWh |
$7,791 291 kW-months/year |
$(-4,106) (-732) MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.1133 ADJUST BURNERS FOR EFFICIENT OPERATION |
Savings: $10,368 Cost: - |
- | - | - | - | $10,368 | 1,848 | - | - |
- - kWh |
- - kW-months/year |
$10,368 1,848 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $541 Cost: $1,832 |
$261 | 6,420 | $255 | 10 | - | - | $25 | - |
$261 6,420 kWh |
$255 10 kW-months/year |
- - MMBtu |
$25 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $5,330 Cost: $3,125 |
- | - | - | - | $5,330 | 950 | - | - |
- - kWh |
- - kW-months/year |
$5,330 950 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2622 REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL |
Savings: $1,894 Cost: $3,900 |
$893 | 21,951 | $1,001 | 37 | - | - | - | - |
$893 21,951 kWh |
$1,001 37 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $187,547 Cost: $351,173 |
$20,890 | 513,303 | $132,912 | 4,965 | $33,720 | 6,010 | $25 | - | $20,890 513,303 kWh |
$132,912 4,965 kW-months/year |
$33,720 6,010 MMBtu |
$25 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $118,921 Cost: $313,320 |
$15,700 | 385,775 | $65,370 | 2,442 | $37,826 | 6,742 | $25 | - | $15,700 385,775 kWh |
$65,370 2,442 kW-months/year |
$37,826 6,742 MMBtu |
$25 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |