Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 1996 |
Principal Product | Iron Castings |
NAICS | n/a |
SIC | 3321 - Gray And Ductile Iron Foundries |
Sales | $10,000,000-$50,000,000 |
# of Employees | 200 |
Plant Area (Sq.Ft.) | 90,000 |
Annual Production | 40,000 Tons |
Production Hrs. Annual | 4,200 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $817,975 | 16,189,039 | kWh | $0.05 |
Electricity Demand | $259,320 | 38,388 | kW-months/year | $6.76 |
Natural Gas | $126,229 | 116,180 | MMBtu | $1.09 |
Other Energy | $1,483,034 | 175,702 | MMBtu | $8.44 |
TOTAL ENERGY COSTS | $2,819,179 | |||
RECOMMENDED SAVINGS* | $91,308 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $46,046 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $4,034 Cost: $4,746 |
$3,226 | 63,892 | $808 | 119 | - | - |
$3,226 63,892 kWh |
$808 119 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $1,906 Cost: $400 |
$1,205 | 23,740 | $701 | 103 | - | - |
$1,205 23,740 kWh |
$701 103 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $37,610 Cost: $85,150 |
- | - | - | - | $37,610 | 36,661 |
- - kWh |
- - kW-months/year |
$37,610 36,661 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $6,708 Cost: $2,145 |
$4,854 | 95,838 | $1,854 | 274 | - | - |
$4,854 95,838 kWh |
$1,854 274 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,012 Cost: - |
$1,630 | 27,843 | $382 | 56 | - | - |
$1,630 27,843 kWh |
$382 56 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT |
Savings: $1,865 Cost: $6,500 |
$1,356 | 26,964 | $509 | 75 | - | - |
$1,356 26,964 kWh |
$509 75 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $5,746 Cost: $12,550 |
- | - | - | - | $5,746 | 5,635 |
- - kWh |
- - kW-months/year |
$5,746 5,635 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2515 USE OPTIMUM THICKNESS INSULATION |
Savings: $26,973 Cost: $3,335 |
$19,191 | 379,543 | $7,782 | 245 | - | - |
$19,191 379,543 kWh |
$7,782 245 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $4,454 Cost: $3,975 |
- | - | - | - | $4,454 | 4,101 |
- - kWh |
- - kW-months/year |
$4,454 4,101 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $91,308 Cost: $118,801 |
$31,462 | 617,820 | $12,036 | 872 | $47,810 | 46,397 | $31,462 617,820 kWh |
$12,036 872 kW-months/year |
$47,810 46,397 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $46,046 Cost: $20,701 |
$30,257 | 594,080 | $11,335 | 769 | $4,454 | 4,101 | $30,257 594,080 kWh |
$11,335 769 kW-months/year |
$4,454 4,101 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |