Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 1999 |
Principal Product | Polystyrene Loosefill |
NAICS | n/a |
SIC | 3085 - Plastics Bottles |
Sales | $1,000,000-$5,000,000 |
# of Employees | 20 |
Plant Area (Sq.Ft.) | 41,000 |
Annual Production | 7,000,000 Units |
Production Hrs. Annual | 4,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $79,222 | 975,674 | kWh | $0.08 |
Electricity Demand | $15,836 | 3,680 | kW-months/year | $4.30 |
Natural Gas | $47,287 | 8,297 | MMBtu | $5.70 |
TOTAL ENERGY COSTS | $163,882 | |||
RECOMMENDED SAVINGS* | $188,310 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $358 Cost: $451 |
$307 | 3,810 | $51 | 12 | - | - | - | - |
$307 3,810 kWh |
$51 12 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $269 Cost: $506 |
$232 | 2,931 | $37 | 9 | - | - | - | - |
$232 2,931 kWh |
$37 9 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $423 Cost: $1,200 |
$365 | 4,396 | $58 | 14 | - | - | - | - |
$365 4,396 kWh |
$58 14 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7133 USE SEPARATE SWITCHES ON PERIMETER LIGHTING WHICH MAY BE TURNED OFF WHEN NATURAL LIGHT IS AVAILABLE |
Savings: $1,455 Cost: $7,000 |
$1,255 | 15,533 | $200 | 46 | - | - | - | - |
$1,255 15,533 kWh |
$200 46 kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $14,305 Cost: $14,475 |
- | - | - | - | $12,555 | - | $1,750 | - |
- - kWh |
- - kW-months/year |
$12,555 - lb |
$1,750 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS |
Savings: $56,000 Cost: - |
- | - | - | - | - | - | $56,000 | - |
- - kWh |
- - kW-months/year |
- - lb |
$56,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $3,500 Cost: $164 |
- | - | - | - | - | - | $3,500 | - |
- - kWh |
- - kW-months/year |
- - lb |
$3,500 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 4.513 RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS |
Savings: $112,000 Cost: $49,860 |
- | - | - | - | - | - | $112,000 | - |
- - kWh |
- - kW-months/year |
- - lb |
$112,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $188,310 Cost: $73,656 |
$2,159 | 26,670 | $346 | 81 | $12,555 | - | $173,250 | - | $2,159 26,670 kWh |
$346 81 kW-months/year |
$12,555 - lb |
$173,250 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - lb |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Administrative Changes |