IAC Assessment: SF0234
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0234
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2002
Principal Product Metal Products
NAICS n/a
SIC 3321 - Gray And Ductile Iron Foundries
Sales $10,000,000-$50,000,000
# of Employees 120
Plant Area (Sq.Ft.) 81,460
Annual Production 1,385 Tons
Production Hrs. Annual 2,125
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $416,011 3,501,220 kWh $0.12
Natural Gas $111,163 10,313 MMBtu $10.78
TOTAL ENERGY COSTS $534,625
RECOMMENDED SAVINGS* $63,010 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $22,626
#|Description Savings
Cost
Status Electricity Usage Administrative Changes Electricity Usage Administrative Changes
$ kWh $ $
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$7,185
Cost:
$300
$7,185 31,959 - - $7,185
31,959
kWh
-
-
$
02: 2.7134 USE PHOTOCELL CONTROLS Savings:
$8,489
Cost:
$6,960
$8,489 52,595 - - $8,489
52,595
kWh
-
-
$
03: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS Savings:
$988
Cost:
$1,250
$988 3,745 - - $988
3,745
kWh
-
-
$
04: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$904
Cost:
$1,304
- - $904 - -
-
kWh
$904
-
$
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$4,974
Cost:
$10,307
$4,974 28,587 - - $4,974
28,587
kWh
-
-
$
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$6,310
Cost:
$14,027
$6,310 31,750 - - $6,310
31,750
kWh
-
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$18,719
Cost:
$46,531
$18,719 108,958 - - $18,719
108,958
kWh
-
-
$
08: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$15,441
Cost:
$49,000
$15,441 (-79,719) - - $15,441
(-79,719)
kWh
-
-
$
TOTAL RECOMMENDED Savings:
$63,010
Cost:
$129,679
$62,106 177,875 $904 - $62,106
177,875
kWh
$904
-
$
TOTAL IMPLEMENTED Savings:
$22,626
Cost:
$49,300
$22,626 (-47,760) - - $22,626
(-47,760)
kWh
-
-
$
Savings
Cost
$ kWh $ $
Electricity Usage Administrative Changes Electricity Usage Administrative Changes