IAC Assessment: SF0258
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0258
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2003
Principal Product Recycled Water, Tertiary Treated Wastewater
NAICS 221310 - Water Supply and Irrigation Systems
SIC 4941 - Water Supply
Sales $5,000,000-$10,000,000
# of Employees 56
Plant Area (Sq.Ft.) 1,500,000
Annual Production 39,000 Thousand Gallons
Production Hrs. Annual 8,736
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $687,992 7,949,767 kWh $0.09
Electricity Demand $184,631 19,284 kW-months/year $9.57
TOTAL ENERGY COSTS $1,088,409
RECOMMENDED SAVINGS* $359,834 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $16,680
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)
$ kWh $ kW-months/year $ lb
01: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$10,511
Cost:
-
$7,305 84,455 $3,206 288 - - $7,305
84,455
kWh
$3,206
288
kW-months/year
-
-
lb
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS Savings:
$2,432
Cost:
$580
$2,211 25,567 $221 25 - - $2,211
25,567
kWh
$221
25
kW-months/year
-
-
lb
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$121,871
Cost:
$70,000
$105,793 1,223,040 $16,078 1,680 - - $105,793
1,223,040
kWh
$16,078
1,680
kW-months/year
-
-
lb
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$4,255
Cost:
$3,120
$3,641 42,092 $614 64 - - $3,641
42,092
kWh
$614
64
kW-months/year
-
-
lb
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$6,169
Cost:
$4,761
$5,413 62,583 $756 87 - - $5,413
62,583
kWh
$756
87
kW-months/year
-
-
lb
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$82,069
Cost:
$76,562
$70,307 812,800 $11,762 1,229 - - $70,307
812,800
kWh
$11,762
1,229
kW-months/year
-
-
lb
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$29,851
Cost:
$48,000
$25,913 299,574 $3,938 411 - - $25,913
299,574
kWh
$3,938
411
kW-months/year
-
-
lb
08: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$12,213
Cost:
$27,140
$10,623 122,806 $1,590 166 - - $10,623
122,806
kWh
$1,590
166
kW-months/year
-
-
lb
09: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS Savings:
$5,950
Cost:
$25,615
$5,165 59,715 $785 82 - - $5,165
59,715
kWh
$785
82
kW-months/year
-
-
lb
10: 3.6112 USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME Savings:
$84,513
Cost:
$145,200
- - - - $84,513 - -
-
kWh
-
-
kW-months/year
$84,513
-
lb
TOTAL RECOMMENDED Savings:
$359,834
Cost:
$400,978
$236,371 2,732,632 $38,950 4,032 $84,513 - $236,371
2,732,632
kWh
$38,950
4,032
kW-months/year
$84,513
-
lb
TOTAL IMPLEMENTED Savings:
$16,680
Cost:
$4,761
$12,718 147,038 $3,962 375 - - $12,718
147,038
kWh
$3,962
375
kW-months/year
-
-
lb
Savings
Cost
$ kWh $ kW-months/year $ lb
Electricity Usage Electricity Demand Solid Waste (non-haz) Electricity Usage Electricity Demand Solid Waste (non-haz)