Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2003 |
Principal Product | Asphalt Roofing Shingles |
NAICS | 324122 - Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952 - Asphalt Felts And Coatings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 79 |
Plant Area (Sq.Ft.) | 267,800 |
Annual Production | 0 Units |
Production Hrs. Annual | 6,960 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $568,833 | 4,467,600 | kWh | $0.13 |
Electricity Demand | $106,196 | 9,684 | kW-months/year | $10.97 |
Natural Gas | $460,999 | 112,442 | MMBtu | $4.10 |
TOTAL ENERGY COSTS | $1,452,665 | |||
RECOMMENDED SAVINGS* | $256,127 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $92,387 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $7,393 Cost: $420 |
$7,393 | 71,642 | - | - | - | - | - | - | - | - |
$7,393 71,642 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,964 Cost: $567 |
$1,964 | 19,035 | - | - | - | - | - | - | - | - |
$1,964 19,035 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $2,225 Cost: $2,760 |
$1,381 | 13,380 | $844 | 77 | - | - | - | - | - | - |
$1,381 13,380 kWh |
$844 77 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $23,846 Cost: $38,640 |
$20,152 | 195,270 | $3,694 | 337 | - | - | - | - | - | - |
$20,152 195,270 kWh |
$3,694 337 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,167 Cost: $8,360 |
$4,367 | 42,317 | $800 | 73 | - | - | - | - | - | - |
$4,367 42,317 kWh |
$800 73 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $8,193 Cost: $15,000 |
$6,580 | 63,761 | $1,613 | 147 | - | - | - | - | - | - |
$6,580 63,761 kWh |
$1,613 147 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $142,307 Cost: $525,000 |
- | - | - | - | $142,307 | 34,794 | - | - | - | - |
- - kWh |
- - kW-months/year |
$142,307 34,794 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $56,959 Cost: $350 |
- | - | - | - | - | - | $56,959 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$56,959 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 4.131 MODIFY PROCESS TO REDUCE MATERIAL USE/COST |
Savings: $8,073 Cost: $20,578 |
- | - | - | - | - | - | - | - | $8,073 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
$8,073 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $256,127 Cost: $611,675 |
$41,837 | 405,405 | $6,951 | 634 | $142,307 | 34,794 | $56,959 | - | $8,073 | - | $41,837 405,405 kWh |
$6,951 634 kW-months/year |
$142,307 34,794 MMBtu |
$56,959 - $ |
$8,073 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $92,387 Cost: $42,737 |
$30,890 | 299,327 | $4,538 | 414 | - | - | $56,959 | - | - | - | $30,890 299,327 kWh |
$4,538 414 kW-months/year |
- - MMBtu |
$56,959 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Natural Gas | Administrative Changes | Primary Raw Material |