IAC logo
IAC Assessment: SF0337
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0337
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2007
Principal Product Drugs of Abuse Test Kits
NAICS 325412 - Pharmaceutical Preparation Manufacturing
SIC 2835 - Diagnostic Substances
Sales $50,000,000-$100,000,000
# of Employees 270
Plant Area (Sq.Ft.) 90,000
Annual Production 45,000,000 Pieces
Production Hrs. Annual 2,340
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $210,970 2,208,699 kWh $0.10
Electricity Demand $90,154 6,546 kW-months/year $13.77
TOTAL ENERGY COSTS $322,052
RECOMMENDED SAVINGS* $69,006 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $17,759
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$9,667
Cost:
-
$9,667 86,009 - - - - $9,667
86,009
kWh
-
-
kW-months/year
-
-
MMBtu
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$50,318
Cost:
$20,000
$10,884 96,818 $39,434 2,070 - - $10,884
96,818
kWh
$39,434
2,070
kW-months/year
-
-
MMBtu
03: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,729
Cost:
$937
- - - - $1,729 131 -
-
kWh
-
-
kW-months/year
$1,729
131
MMBtu
04: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$3,650
Cost:
$3,344
$1,990 16,990 $1,660 87 - - $1,990
16,990
kWh
$1,660
87
kW-months/year
-
-
MMBtu
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,534
Cost:
$3,510
$821 7,301 $713 37 - - $821
7,301
kWh
$713
37
kW-months/year
-
-
MMBtu
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,179
Cost:
$3,376
$980 8,711 $199 10 - - $980
8,711
kWh
$199
10
kW-months/year
-
-
MMBtu
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$929
Cost:
$3,460
$497 4,418 $432 23 - - $497
4,418
kWh
$432
23
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$69,006
Cost:
$34,627
$24,839 220,247 $42,438 2,227 $1,729 131 $24,839
220,247
kWh
$42,438
2,227
kW-months/year
$1,729
131
MMBtu
TOTAL IMPLEMENTED Savings:
$17,759
Cost:
$11,167
$13,458 119,011 $2,572 134 $1,729 131 $13,458
119,011
kWh
$2,572
134
kW-months/year
$1,729
131
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas