IAC Assessment: SF0432
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SF0432
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Francisco State University
Assessment Year 2013
Principal Product Treated waste water
NAICS 221320 - Sewage Treatment Facilities
SIC 4952 - Sewerage Systems
Sales $10,000,000-$50,000,000
# of Employees 132
Plant Area (Sq.Ft.) 1,431,654
Annual Production 8,961 Units
Production Hrs. Annual 8,760
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,274,909 15,825,648 kWh $0.08
Electricity Demand $469,613 29,171 kW-months/year $16.10
Electricity Fees $23,018 - $ -
Natural Gas $20,171 2,229 MMBtu $9.05
TOTAL ENERGY COSTS $1,787,711
RECOMMENDED SAVINGS* $220,322 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $143,112
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas
$ kWh $ kW-months/year $ MMBtu
01: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS Savings:
$11,539
Cost:
-
$571 7,000 - - $10,968 1,212 $571
7,000
kWh
-
-
kW-months/year
$10,968
1,212
MMBtu
02: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$5,729
Cost:
-
$5,729 70,248 - - - - $5,729
70,248
kWh
-
-
kW-months/year
-
-
MMBtu
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$59,942
Cost:
$176,082
$46,682 572,432 $13,260 784 - - $46,682
572,432
kWh
$13,260
784
kW-months/year
-
-
MMBtu
04: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$70,722
Cost:
$226,685
$55,077 675,381 $15,645 925 - - $55,077
675,381
kWh
$15,645
925
kW-months/year
-
-
MMBtu
05: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$20,321
Cost:
$22,006
$15,826 194,061 $4,495 266 - - $15,826
194,061
kWh
$4,495
266
kW-months/year
-
-
MMBtu
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$41,285
Cost:
$208,561
$34,260 420,112 $7,025 415 - - $34,260
420,112
kWh
$7,025
415
kW-months/year
-
-
MMBtu
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$10,784
Cost:
$5,853
$8,398 102,984 $2,386 142 - - $8,398
102,984
kWh
$2,386
142
kW-months/year
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$220,322
Cost:
$639,187
$166,543 2,042,218 $42,811 2,532 $10,968 1,212 $166,543
2,042,218
kWh
$42,811
2,532
kW-months/year
$10,968
1,212
MMBtu
TOTAL IMPLEMENTED Savings:
$143,112
Cost:
$463,105
$113,561 1,392,538 $29,551 1,748 - - $113,561
1,392,538
kWh
$29,551
1,748
kW-months/year
-
-
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ MMBtu
Electricity Usage Electricity Demand Natural Gas Electricity Usage Electricity Demand Natural Gas