Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2016 |
Principal Product | Treated Wastewater, Recycled Water |
NAICS | 562211 - Hazardous Waste Treatment and Disposal |
SIC | 4953 - Refuse Systems |
Sales | $10,000,000-$50,000,000 |
# of Employees | 75 |
Plant Area (Sq.Ft.) | 1,600,000 |
Annual Production | 4,380,000 Thousand Gallons |
Production Hrs. Annual | 8,760 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $384,745 | 3,702,913 | kWh | $0.10 |
Electricity Demand | $364,805 | 18,058 | kW-months/year | $20.20 |
Natural Gas | $77,129 | 23,874 | MMBtu | $3.23 |
TOTAL ENERGY COSTS | $826,679 | |||
RECOMMENDED SAVINGS* | $151,881 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $151,881 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $6,446 Cost: $90 |
$5,090 | 48,989 | $1,356 | 67 | - | - | - | - | - | - |
$5,090 48,989 kWh |
$1,356 67 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $16,188 Cost: - |
$12,036 | 115,845 | - | - | $4,152 | 1,286 | - | - | - | - |
$12,036 115,845 kWh |
- - kW-months/year |
$4,152 1,286 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $6,291 Cost: $2,526 |
$6,291 | 60,544 | - | - | - | - | - | - | - | - |
$6,291 60,544 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $35,873 Cost: $39,842 |
$31,693 | 315,046 | $5,216 | 258 | - | - | $1,014 | - | $(-2,050) | - |
$31,693 315,046 kWh |
$5,216 258 kW-months/year |
- - MMBtu |
$1,014 - $ |
$(-2,050) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $86,200 Cost: $179,607 |
$68,071 | 655,160 | $18,129 | 900 | - | - | - | - | - | - |
$68,071 655,160 kWh |
$18,129 900 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $883 Cost: $3,334 |
$334 | 3,211 | $549 | 27 | - | - | - | - | - | - |
$334 3,211 kWh |
$549 27 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $151,881 Cost: $225,399 |
$123,515 | 1,198,795 | $25,250 | 1,252 | $4,152 | 1,286 | $1,014 | - | $(-2,050) | - | $123,515 1,198,795 kWh |
$25,250 1,252 kW-months/year |
$4,152 1,286 MMBtu |
$1,014 - $ |
$(-2,050) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $151,881 Cost: $225,399 |
$123,515 | 1,198,795 | $25,250 | 1,252 | $4,152 | 1,286 | $1,014 | - | $(-2,050) | - | $123,515 1,198,795 kWh |
$25,250 1,252 kW-months/year |
$4,152 1,286 MMBtu |
$1,014 - $ |
$(-2,050) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost |