Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2016 |
Principal Product | wine |
NAICS | 312130 - Wineries |
SIC | 2084 - Wines, Brandy, And Brandy Spirits |
Sales | $10,000,000-$50,000,000 |
# of Employees | 30 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 450,000 Units |
Production Hrs. Annual | 4,216 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $129,628 | 697,536 | kWh | $0.19 |
LPG | $15,879 | 1,739 | MMBtu | $9.13 |
TOTAL ENERGY COSTS | $145,507 | |||
RECOMMENDED SAVINGS* | $76,315 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $23,425 |
#|Description |
Savings Cost |
Status | Electricity Usage | Personnel Changes | Ancillary Material Cost | Electricity Usage | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE |
Savings: $9,190 Cost: $300 |
$9,190 | 30,772 | - | - | - | - |
$9,190 30,772 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $25,960 Cost: $7,975 |
$25,960 | 86,922 | - | - | - | - |
$25,960 86,922 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $17,740 Cost: $6,235 |
$17,740 | 59,400 | - | - | - | - |
$17,740 59,400 kWh |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $23,425 Cost: $15,337 |
$20,714 | 69,158 | $1,371 | - | $1,340 | - |
$20,714 69,158 kWh |
$1,371 - $ |
$1,340 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $76,315 Cost: $29,847 |
$73,604 | 246,252 | $1,371 | - | $1,340 | - | $73,604 246,252 kWh |
$1,371 - $ |
$1,340 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $23,425 Cost: $15,337 |
$20,714 | 69,158 | $1,371 | - | $1,340 | - | $20,714 69,158 kWh |
$1,371 - $ |
$1,340 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Personnel Changes | Ancillary Material Cost | Electricity Usage | Personnel Changes | Ancillary Material Cost |