Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2018 |
Principal Product | Energetic Devices for Aircraft, Rockets, and Launch Devices |
NAICS | 336413 - Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728 - Aircraft Parts And Equipment, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 180,000 |
Annual Production | 5,000 Units |
Production Hrs. Annual | 2,678 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $259,293 | 2,360,427 | kWh | $0.11 |
Electricity Demand | $188,726 | 7,452 | kW-months/year | $25.33 |
Fuel Oil #1 | $58,361 | 2,441 | MMBtu | $23.91 |
TOTAL ENERGY COSTS | $506,380 | |||
RECOMMENDED SAVINGS* | $38,235 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $38,235 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #1 | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Fuel Oil #1 | Personnel Changes | Primary Raw Material | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $872 Cost: $204 |
$872 | 7,941 | - | - | - | - | - | - | - | - |
$872 7,941 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,653 Cost: $386 |
- | - | - | - | $1,653 | 69 | - | - | - | - |
- - kWh |
- - kW-months/year |
$1,653 69 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $35,710 Cost: $163,709 |
$18,391 | 167,418 | $16,557 | 654 | - | - | $1,987 | - | $(-1,225) | - |
$18,391 167,418 kWh |
$16,557 654 kW-months/year |
- - MMBtu |
$1,987 - $ |
$(-1,225) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $38,235 Cost: $164,299 |
$19,263 | 175,359 | $16,557 | 654 | $1,653 | 69 | $1,987 | - | $(-1,225) | - | $19,263 175,359 kWh |
$16,557 654 kW-months/year |
$1,653 69 MMBtu |
$1,987 - $ |
$(-1,225) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $38,235 Cost: $164,299 |
$19,263 | 175,359 | $16,557 | 654 | $1,653 | 69 | $1,987 | - | $(-1,225) | - | $19,263 175,359 kWh |
$16,557 654 kW-months/year |
$1,653 69 MMBtu |
$1,987 - $ |
$(-1,225) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #1 | Personnel Changes | Primary Raw Material | Electricity Usage | Electricity Demand | Fuel Oil #1 | Personnel Changes | Primary Raw Material |