Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2018 |
Principal Product | Structural Steel |
NAICS | 332312 - Fabricated Structural Metal Manufacturing |
SIC | 3441 - Fabricated Structural Metal |
Sales | $10,000,000-$50,000,000 |
# of Employees | 55 |
Plant Area (Sq.Ft.) | 283,000 |
Annual Production | 5,000 Tons |
Production Hrs. Annual | 3,120 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $245,655 | 1,098,760 | kWh | $0.22 |
Electricity Fees | $31,644 | - | $ | - |
Natural Gas | $7,091 | 481 | MMBtu | $14.75 |
TOTAL ENERGY COSTS | $284,390 | |||
RECOMMENDED SAVINGS* | $256,176 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $128,472 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $49,766 Cost: - |
$49,766 | 197,193 | - | - | - | - | - | - | - | - | - | - |
$49,766 197,193 kWh |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $16,260 Cost: - |
$17,220 | 68,238 | - | - | - | - | $(-960) | - | - | - | - | - |
$17,220 68,238 kWh |
- - $ |
- - MMBtu |
$(-960) - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,078 Cost: $160 |
$2,078 | 8,232 | - | - | - | - | - | - | - | - | - | - |
$2,078 8,232 kWh |
- - $ |
- - MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $3,086 Cost: $354 |
$80 | 315 | - | - | $3,006 | 204 | - | - | - | - | - | - |
$80 315 kWh |
- - $ |
$3,006 204 MMBtu |
- - $ |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $60,368 Cost: $59,620 |
$57,443 | 227,614 | - | - | - | - | $2,190 | - | - | - | $735 | - |
$57,443 227,614 kWh |
- - $ |
- - MMBtu |
$2,190 - $ |
- - $ |
$735 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $124,618 Cost: $491,526 |
$115,232 | 456,598 | $8,498 | - | - | - | - | - | $888 | - | - | - |
$115,232 456,598 kWh |
$8,498 - $ |
- - MMBtu |
- - $ |
$888 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $256,176 Cost: $551,660 |
$241,819 | 958,190 | $8,498 | - | $3,006 | 204 | $1,230 | - | $888 | - | $735 | - | $241,819 958,190 kWh |
$8,498 - $ |
$3,006 204 MMBtu |
$1,230 - $ |
$888 - $ |
$735 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $128,472 Cost: $59,780 |
$126,507 | 501,277 | - | - | - | - | $1,230 | - | - | - | $735 | - | $126,507 501,277 kWh |
- - $ |
- - MMBtu |
$1,230 - $ |
- - $ |
$735 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | $ | $ | MMBtu | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Ancillary Material Cost |