Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2018 |
Principal Product | Wine |
NAICS | 312130 - Wineries |
SIC | 2084 - Wines, Brandy, And Brandy Spirits |
Sales | $1,000,000-$5,000,000 |
# of Employees | 18 |
Plant Area (Sq.Ft.) | 45,000 |
Annual Production | 100 Thousand Gallons |
Production Hrs. Annual | 3,228 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $67,763 | 582,883 | kWh | $0.12 |
Electricity Demand | $29,179 | 2,220 | kW-months/year | $13.14 |
LPG | $35,166 | 1,667 | MMBtu | $21.10 |
TOTAL ENERGY COSTS | $132,108 | |||
RECOMMENDED SAVINGS* | $25,413 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $25,413 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | LPG | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | LPG | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $9,136 Cost: $1,467 |
$2,235 | 19,225 | - | - | $6,901 | 327 | - | - | - | - |
$2,235 19,225 kWh |
- - kW-months/year |
$6,901 327 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $283 Cost: $150 |
$242 | 2,081 | $41 | 3 | - | - | - | - | - | - |
$242 2,081 kWh |
$41 3 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $10,163 Cost: $17,090 |
$5,648 | 48,583 | $2,327 | 178 | - | - | $2,135 | - | $53 | - |
$5,648 48,583 kWh |
$2,327 178 kW-months/year |
- - MMBtu |
$2,135 - $ |
$53 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $631 Cost: $1,040 |
- | - | - | - | $631 | 30 | - | - | - | - |
- - kWh |
- - kW-months/year |
$631 30 MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2691 SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS |
Savings: $5,200 Cost: $13,166 |
$5,200 | 44,729 | - | - | - | - | - | - | - | - |
$5,200 44,729 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $25,413 Cost: $32,913 |
$13,325 | 114,618 | $2,368 | 181 | $7,532 | 357 | $2,135 | - | $53 | - | $13,325 114,618 kWh |
$2,368 181 kW-months/year |
$7,532 357 MMBtu |
$2,135 - $ |
$53 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $25,413 Cost: $32,913 |
$13,325 | 114,618 | $2,368 | 181 | $7,532 | 357 | $2,135 | - | $53 | - | $13,325 114,618 kWh |
$2,368 181 kW-months/year |
$7,532 357 MMBtu |
$2,135 - $ |
$53 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | LPG | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | LPG | Personnel Changes | Ancillary Material Cost |