Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2020 |
Principal Product | Specialty Food Products |
NAICS | 311999 - All Other Miscellaneous Food Manufacturing |
SIC | 2099 - Food Preparations, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 24,498 |
Annual Production | 200,000 Pounds |
Production Hrs. Annual | 4,160 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $197,315 | 1,122,123 | kWh | $0.18 |
Electricity Demand | $119,796 | 2,972 | kW-months/year | $40.31 |
Electricity Fees | $(-87,971) | - | $ | - |
Natural Gas | $90,417 | 8,946 | MMBtu | $10.11 |
TOTAL ENERGY COSTS | $319,557 | |||
RECOMMENDED SAVINGS* | $572,005 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $58,727 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Personnel Changes | Electricity Usage | Natural Gas | Personnel Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,084 Cost: - |
$6,344 | 33,604 | - | - | $(-1,260) | - |
$6,344 33,604 kWh |
- - MMBtu |
$(-1,260) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,257 Cost: $1,080 |
- | - | $1,257 | 125 | - | - |
- - kWh |
$1,257 125 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS |
Savings: $3,734 Cost: $3,930 |
$3,734 | 19,778 | - | - | - | - |
$3,734 19,778 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $450,171 Cost: $750,000 |
$450,171 | 249,600 | - | - | - | - |
$450,171 249,600 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $26,221 Cost: $33,106 |
$26,221 | 133,672 | - | - | - | - |
$26,221 133,672 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $7,764 Cost: $20,616 |
$7,764 | 41,121 | - | - | - | - |
$7,764 41,121 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1224 REPLACE BOILER |
Savings: $14,667 Cost: $114,810 |
$1,524 | 8,071 | $13,143 | 1,300 | - | - |
$1,524 8,071 kWh |
$13,143 1,300 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $63,107 Cost: $268,469 |
$63,107 | 334,254 | - | - | - | - |
$63,107 334,254 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $572,005 Cost: $1,192,011 |
$558,865 | 820,100 | $14,400 | 1,425 | $(-1,260) | - | $558,865 820,100 kWh |
$14,400 1,425 MMBtu |
$(-1,260) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $58,727 Cost: $173,542 |
$45,587 | 236,246 | $14,400 | 1,425 | $(-1,260) | - | $45,587 236,246 kWh |
$14,400 1,425 MMBtu |
$(-1,260) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Personnel Changes | Electricity Usage | Natural Gas | Personnel Changes |