Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Francisco State University |
---|---|
Assessment Year | 2024 |
Principal Product | Fluid Milks |
NAICS | 311511 - Fluid Milk Manufacturing |
SIC | 2026 - Fluid Milk |
Sales | $100,000,000-$500,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 150,000 |
Annual Production | 14,500,000 Units |
Production Hrs. Annual | 8,400 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $882,039 | 12,598,980 | kWh | $0.07 |
Electricity Demand | $589,421 | 30,957 | kW-months/year | $19.04 |
Electricity Fees | $121,981 | - | $ | - |
Natural Gas | $1,494,906 | 198,921 | MMBtu | $7.52 |
TOTAL ENERGY COSTS | $4,128,300 | |||
RECOMMENDED SAVINGS* | $744,354 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Usage | Water Disposal | Personnel Changes | Primary Raw Material | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Usage | Water Disposal | Personnel Changes | Primary Raw Material | Primary Product | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $4,612 Cost: - |
- | - | - | - | - | - | $5,314 | 707 | $178 | 62 | - | - | $(-880) | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$5,314 707 MMBtu |
$178 62 Tgal |
- - Tgal |
$(-880) - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $5,589 Cost: $220 |
$4,074 | 55,635 | $1,515 | 79 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$4,074 55,635 kWh |
$1,515 79 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $241 Cost: - |
- | - | - | - | $241 | - | - | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$241 - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE |
Savings: $39,174 Cost: $7,044 |
- | - | - | - | - | - | - | - | $3,775 | 1,314 | $35,399 | 1,314 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$3,775 1,314 Tgal |
$35,399 1,314 Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE |
Savings: $7,106 Cost: $2,700 |
$789 | 9,905 | - | - | - | - | $6,317 | 840 | - | - | - | - | - | - | - | - | - | - |
$789 9,905 kWh |
- - kW-months/year |
- - $ |
$6,317 840 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $90,155 Cost: $37,058 |
- | - | - | - | - | - | - | - | $8,688 | 3,024 | $81,467 | 3,024 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$8,688 3,024 Tgal |
$81,467 3,024 Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2111 INSTALL STEAM TRAP |
Savings: $531,211 Cost: $270,719 |
- | - | - | - | - | - | $137,992 | 18,350 | $40,197 | 13,991 | $353,022 | 13,104 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$137,992 18,350 MMBtu |
$40,197 13,991 Tgal |
$353,022 13,104 Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $6,389 Cost: $4,926 |
$6,389 | 80,167 | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$6,389 80,167 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,201 Cost: $2,875 |
- | - | - | - | - | - | $2,201 | 293 | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$2,201 293 MMBtu |
- - Tgal |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $292 Cost: $785 |
$145 | 1,687 | - | - | - | - | - | - | - | - | - | - | $58 | - | $89 | - | - | - |
$145 1,687 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
$58 - $ |
$89 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.132 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST |
Savings: $52,391 Cost: $160,125 |
$(-7,479) | (-93,845) | - | - | - | - | - | - | - | - | - | - | - | - | - | - | $59,870 | - |
$(-7,479) (-93,845) kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
- - $ |
$59,870 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $4,993 Cost: $16,268 |
$3,723 | 46,717 | $1,270 | 67 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$3,723 46,717 kWh |
$1,270 67 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $744,354 Cost: $502,720 |
$7,641 | 100,266 | $2,785 | 146 | $241 | - | $151,824 | 20,189 | $52,838 | 18,391 | $469,888 | 17,442 | $(-822) | - | $89 | - | $59,870 | - | $7,641 100,266 kWh |
$2,785 146 kW-months/year |
$241 - $ |
$151,824 20,189 MMBtu |
$52,838 18,391 Tgal |
$469,888 17,442 Tgal |
$(-822) - $ |
$89 - $ |
$59,870 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - Tgal |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | Tgal | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Usage | Water Disposal | Personnel Changes | Primary Raw Material | Primary Product | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Usage | Water Disposal | Personnel Changes | Primary Raw Material | Primary Product |