Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Jose State University |
---|---|
Assessment Year | 2023 |
Principal Product | Roofing; Pond Liners; Custom Products |
NAICS | 326299 - All Other Rubber Product Manufacturing |
SIC | 3069 - Fabricated Rubber Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 60 |
Plant Area (Sq.Ft.) | 120,000 |
Annual Production | 9,598,000 Pounds |
Production Hrs. Annual | 4,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $389,107 | 2,529,775 | kWh | $0.15 |
Electricity Demand | $362,519 | 9,168 | kW-months/year | $39.54 |
Electricity Fees | $(-316,732) | - | $ | - |
Natural Gas | $97,675 | 12,439 | MMBtu | $7.85 |
TOTAL ENERGY COSTS | $532,569 | |||
RECOMMENDED SAVINGS* | $165,840 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.9114 USE SOLAR HEAT TO MAKE ELECTRICTY |
Savings: $132,467 Cost: $665,395 |
$119,928 | 779,718 | $12,539 | 318 | - | - |
$119,928 779,718 kWh |
$12,539 318 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,014 Cost: $7,324 |
$2,147 | 13,956 | $2,867 | 73 | - | - |
$2,147 13,956 kWh |
$2,867 73 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $798 Cost: $2,977 |
$798 | 5,188 | - | - | - | - |
$798 5,188 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $1,078 Cost: $7,298 |
- | - | - | - | $1,078 | 137 |
- - kWh |
- - kW-months/year |
$1,078 137 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $14,647 Cost: $23,000 |
$14,647 | 95,226 | - | - | - | - |
$14,647 95,226 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,713 Cost: $4,600 |
$2,713 | 17,637 | - | - | - | - |
$2,713 17,637 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT |
Savings: $8,791 Cost: $39,456 |
- | - | - | - | $8,791 | 1,120 |
- - kWh |
- - kW-months/year |
$8,791 1,120 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $332 Cost: $1,762 |
- | - | - | - | $332 | 42 |
- - kWh |
- - kW-months/year |
$332 42 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $165,840 Cost: $751,812 |
$140,233 | 911,725 | $15,406 | 391 | $10,201 | 1,299 | $140,233 911,725 kWh |
$15,406 391 kW-months/year |
$10,201 1,299 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |