Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2001 |
Principal Product | brake pistons |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 41,650 |
Annual Production | 16,000 Pieces |
Production Hrs. Annual | 5,760 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $165,323 | 2,570,243 | kWh | $0.06 |
Electricity Demand | $44,091 | 5,636 | kW-months/year | $7.82 |
Electricity Fees | $6,385 | - | $ | - |
Natural Gas | $62,812 | 7,833 | MMBtu | $8.02 |
TOTAL ENERGY COSTS | $278,611 | |||
RECOMMENDED SAVINGS* | $78,883 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $63,651 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $1,561 Cost: - |
- | - | - | - | - | - | - | - | - | - | $1,561 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
$1,561 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $6,467 Cost: - |
$6,467 | 107,784 | - | - | - | - | - | - | - | - | - | - |
$6,467 107,784 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $6,122 Cost: $20,070 |
$6,122 | 102,036 | - | - | - | - | - | - | - | - | - | - |
$6,122 102,036 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,096 Cost: $665 |
$1,698 | 28,309 | $398 | 51 | - | - | - | - | - | - | - | - |
$1,698 28,309 kWh |
$398 51 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,687 Cost: $342 |
$1,328 | 22,136 | $359 | 46 | - | - | - | - | - | - | - | - |
$1,328 22,136 kWh |
$359 46 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,313 Cost: $840 |
$1,819 | 30,319 | $494 | 63 | - | - | - | - | - | - | - | - |
$1,819 30,319 kWh |
$494 63 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $920 Cost: $3,275 |
$724 | 12,080 | $196 | 25 | - | - | - | - | - | - | - | - |
$724 12,080 kWh |
$196 25 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $4,470 Cost: $6,200 |
- | - | - | - | $4,470 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,470 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.4111 USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION |
Savings: $34,312 Cost: - |
$29,030 | 483,840 | $7,882 | 1,008 | - | - | - | - | $(-2,600) | - | - | - |
$29,030 483,840 kWh |
$7,882 1,008 kW-months/year |
- - $ |
- - MMBtu |
$(-2,600) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $8,216 Cost: $9,990 |
- | - | - | - | - | - | $8,216 | 1,053 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$8,216 1,053 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $10,719 Cost: $760 |
- | - | - | - | - | - | $10,719 | 1,374 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$10,719 1,374 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $78,883 Cost: $42,142 |
$47,188 | 786,504 | $9,329 | 1,193 | $4,470 | - | $18,935 | 2,427 | $(-2,600) | - | $1,561 | - | $47,188 786,504 kWh |
$9,329 1,193 kW-months/year |
$4,470 - $ |
$18,935 2,427 MMBtu |
$(-2,600) - $ |
$1,561 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $63,651 Cost: $27,030 |
$41,619 | 693,660 | $7,882 | 1,008 | $4,470 | - | $10,719 | 1,374 | $(-2,600) | - | $1,561 | - | $41,619 693,660 kWh |
$7,882 1,008 kW-months/year |
$4,470 - $ |
$10,719 1,374 MMBtu |
$(-2,600) - $ |
$1,561 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Ancillary Material Cost | One-time Revenue or Avoided Cost |