IAC Assessment: SU0214
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0214
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2005
Principal Product HVAC Equipment
NAICS 333414 - Heating Equipment (except Warm Air Furnaces) Manufacturing
SIC 3585 - Refrigeration And Heating Equipment
Sales $50,000,000-$100,000,000
# of Employees 429
Plant Area (Sq.Ft.) 435,000
Annual Production 20,000 Pieces
Production Hrs. Annual 4,284
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $616,694 7,708,680 kWh $0.08
Electricity Demand $850,752 70,896 kW-months/year $12.00
Natural Gas $647,748 91,762 MMBtu $7.06
TOTAL ENERGY COSTS $2,203,505
RECOMMENDED SAVINGS* $34,534 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $31,662
#|Description Savings
Cost
Status Electricity Usage Electricity Demand One-time Revenue or Avoided Cost Electricity Usage Electricity Demand One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$243
Cost:
-
$135 1,692 $108 9 - - $135
1,692
kWh
$108
9
kW-months/year
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$7,788
Cost:
-
$5,484 68,544 $2,304 192 - - $5,484
68,544
kWh
$2,304
192
kW-months/year
-
-
$
03: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$9,637
Cost:
-
$5,233 65,417 $4,404 367 - - $5,233
65,417
kWh
$4,404
367
kW-months/year
-
-
$
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$8,167
Cost:
$595
$4,435 55,435 $3,732 311 - - $4,435
55,435
kWh
$3,732
311
kW-months/year
-
-
$
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$6,070
Cost:
$1,125
$4,270 53,379 $1,800 150 - - $4,270
53,379
kWh
$1,800
150
kW-months/year
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,629
Cost:
$1,881
$746 9,321 $156 13 $1,727 - $746
9,321
kWh
$156
13
kW-months/year
$1,727
-
$
TOTAL RECOMMENDED Savings:
$34,534
Cost:
$3,601
$20,303 253,788 $12,504 1,042 $1,727 - $20,303
253,788
kWh
$12,504
1,042
kW-months/year
$1,727
-
$
TOTAL IMPLEMENTED Savings:
$31,662
Cost:
$1,720
$19,422 242,775 $12,240 1,020 - - $19,422
242,775
kWh
$12,240
1,020
kW-months/year
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand One-time Revenue or Avoided Cost Electricity Usage Electricity Demand One-time Revenue or Avoided Cost