IAC logo
IAC Assessment: SU0216
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0216
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2005
Principal Product Steel Windows and Doors
NAICS 332321 - Metal Window and Door Manufacturing
SIC 3442 - Metal Doors, Sash, And Trim
Sales $10,000,000-$50,000,000
# of Employees 250
Plant Area (Sq.Ft.) 200,831
Annual Production 10,000 Pieces
Production Hrs. Annual 4,290
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $100,515 2,746,925 kWh $0.04
Electricity Demand $35,832 12,055 kW-months/year $2.97
Electricity Fees $7,771 - $ -
Natural Gas $61,571 49,776 MMBtu $1.24
TOTAL ENERGY COSTS $205,689
RECOMMENDED SAVINGS* $70,940 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $66,365
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Electricity Usage Electricity Demand Personnel Changes
$ kWh $ kW-months/year $ $
01: 2.4321 UPGRADE OBSOLETE EQUIPMENT Savings:
$3,046
Cost:
-
$2,455 66,360 $591 199 - - $2,455
66,360
kWh
$591
199
kW-months/year
-
-
$
02: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$103
Cost:
-
$76 2,054 $27 9 - - $76
2,054
kWh
$27
9
kW-months/year
-
-
$
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$580
Cost:
$294
$473 12,784 $107 36 - - $473
12,784
kWh
$107
36
kW-months/year
-
-
$
04: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$193
Cost:
$300
$140 3,796 $53 18 - - $140
3,796
kWh
$53
18
kW-months/year
-
-
$
05: 4.4310 TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY Savings:
$60,060
Cost:
$134,400
- - - - $60,060 - -
-
kWh
-
-
kW-months/year
$60,060
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$416
Cost:
$981
$104 2,804 $12 4 $300 - $104
2,804
kWh
$12
4
kW-months/year
$300
-
$
07: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$1,140
Cost:
$3,550
$831 22,464 $309 104 - - $831
22,464
kWh
$309
104
kW-months/year
-
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$5,013
Cost:
$17,360
$4,095 110,682 $918 309 - - $4,095
110,682
kWh
$918
309
kW-months/year
-
-
$
09: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES Savings:
$389
Cost:
$1,520
$350 9,461 $39 13 - - $350
9,461
kWh
$39
13
kW-months/year
-
-
$
TOTAL RECOMMENDED Savings:
$70,940
Cost:
$158,405
$8,524 230,405 $2,056 692 $60,360 - $8,524
230,405
kWh
$2,056
692
kW-months/year
$60,360
-
$
TOTAL IMPLEMENTED Savings:
$66,365
Cost:
$153,335
$4,888 132,120 $1,117 376 $60,360 - $4,888
132,120
kWh
$1,117
376
kW-months/year
$60,360
-
$
Savings
Cost
$ kWh $ kW-months/year $ $
Electricity Usage Electricity Demand Personnel Changes Electricity Usage Electricity Demand Personnel Changes