IAC Assessment: SU0225
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0225
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2006
Principal Product Bread, roll, donut, muffin, bagel
NAICS 311812 - Commercial Bakeries
SIC 2051 - Bread, Cake, And Related Products
Sales $10,000,000-$50,000,000
# of Employees 190
Plant Area (Sq.Ft.) 177,000
Annual Production 57,083,000 Pounds
Production Hrs. Annual 8,760
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $726,555 8,971,200 kWh $0.08
Electricity Demand $259,384 20,440 kW-months/year $12.69
Electricity Fees $15,595 - $ -
Natural Gas $320,958 36,644 MMBtu $8.76
TOTAL ENERGY COSTS $1,322,492
RECOMMENDED SAVINGS* $132,695 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $116,197
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Administrative Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Administrative Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $ $ $
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$35,891
Cost:
-
- - - - - - - - $35,891 - - - -
-
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
$35,891
-
$
-
-
$
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$16,498
Cost:
-
$13,580 167,666 $2,918 230 - - - - - - - - $13,580
167,666
kWh
$2,918
230
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
03: 2.4314 USE SYNTHETIC LUBRICANT Savings:
$12,425
Cost:
-
$9,849 121,590 $2,576 203 - - - - - - - - $9,849
121,590
kWh
$2,576
203
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
04: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$4,730
Cost:
-
$3,804 46,960 $926 73 - - - - - - - - $3,804
46,960
kWh
$926
73
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$23,287
Cost:
$1,708
- - - - - - $23,287 2,720 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$23,287
2,720
MMBtu
-
-
$
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$8,994
Cost:
$1,058
$7,408 91,454 $1,586 125 - - - - - - - - $7,408
91,454
kWh
$1,586
125
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
07: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$3,373
Cost:
$250
- - - - - - $3,373 385 - - - - -
-
kWh
-
-
kW-months/year
-
-
$
$3,373
385
MMBtu
-
-
$
-
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$606
Cost:
$653
$230 2,838 $51 4 - - - - $216 - $109 - $230
2,838
kWh
$51
4
kW-months/year
-
-
$
-
-
MMBtu
$216
-
$
$109
-
$
09: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$471
Cost:
$532
$471 5,816 - - - - - - - - - - $471
5,816
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
10: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$16,864
Cost:
$20,100
$13,235 163,388 $3,629 286 - - - - - - - - $13,235
163,388
kWh
$3,629
286
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
11: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$9,250
Cost:
$12,757
- - - - $9,250 - - - - - - - -
-
kWh
-
-
kW-months/year
$9,250
-
$
-
-
MMBtu
-
-
$
-
-
$
12: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES Savings:
$306
Cost:
$515
$255 3,154 $51 4 - - - - - - - - $255
3,154
kWh
$51
4
kW-months/year
-
-
$
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$132,695
Cost:
$37,573
$48,832 602,866 $11,737 925 $9,250 - $26,660 3,105 $36,107 - $109 - $48,832
602,866
kWh
$11,737
925
kW-months/year
$9,250
-
$
$26,660
3,105
MMBtu
$36,107
-
$
$109
-
$
TOTAL IMPLEMENTED Savings:
$116,197
Cost:
$37,573
$35,252 435,200 $8,819 695 $9,250 - $26,660 3,105 $36,107 - $109 - $35,252
435,200
kWh
$8,819
695
kW-months/year
$9,250
-
$
$26,660
3,105
MMBtu
$36,107
-
$
$109
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Natural Gas Administrative Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Electricity Fees Natural Gas Administrative Changes One-time Revenue or Avoided Cost