Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2006 |
Principal Product | Cable Connectors / Filters |
NAICS | 332721 - Precision Turned Product Manufacturing |
SIC | 3451 - Screw Machine Products |
Sales | $50,000,000-$100,000,000 |
# of Employees | 490 |
Plant Area (Sq.Ft.) | 106,000 |
Annual Production | 0 Units |
Production Hrs. Annual | 8,736 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $499,528 | 6,598,400 | kWh | $0.08 |
Electricity Demand | $190,650 | 13,476 | kW-months/year | $14.15 |
Electricity Fees | $15,152 | - | $ | - |
Natural Gas | $68,915 | 8,884 | MMBtu | $7.76 |
TOTAL ENERGY COSTS | $774,245 | |||
RECOMMENDED SAVINGS* | $1,838,514 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $1,838,514 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Ancillary Material Cost | Increase in Production | Electricity Usage | Electricity Demand | Ancillary Material Cost | Increase in Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | % | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $1,378 Cost: - |
- | - | - | - | $1,378 | - | - | - |
- - kWh |
- - kW-months/year |
$1,378 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4224 UPGRADE CONTROLS ON COMPRESSORS |
Savings: $31,676 Cost: $40,711 |
$18,262 | 240,296 | $13,414 | 948 | - | - | - | - |
$18,262 240,296 kWh |
$13,414 948 kW-months/year |
- - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $39,585 Cost: $111,774 |
$13,113 | 172,536 | $3,353 | 237 | $23,119 | - | - | - |
$13,113 172,536 kWh |
$3,353 237 kW-months/year |
$23,119 - $ |
- - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.2176 INCREASE USE OF AUTOMATION |
Savings: $1,765,875 Cost: $3,500,000 |
$(-19,606) | (-257,982) | $(-5,009) | (-354) | $1,363,440 | - | $427,050 | - |
$(-19,606) (-257,982) kWh |
$(-5,009) (-354) kW-months/year |
$1,363,440 - $ |
$427,050 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,838,514 Cost: $3,652,485 |
$11,769 | 154,850 | $11,758 | 831 | $1,387,937 | - | $427,050 | - | $11,769 154,850 kWh |
$11,758 831 kW-months/year |
$1,387,937 - $ |
$427,050 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $1,838,514 Cost: $3,652,485 |
$11,769 | 154,850 | $11,758 | 831 | $1,387,937 | - | $427,050 | - | $11,769 154,850 kWh |
$11,758 831 kW-months/year |
$1,387,937 - $ |
$427,050 - % |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | % | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Ancillary Material Cost | Increase in Production | Electricity Usage | Electricity Demand | Ancillary Material Cost | Increase in Production |