IAC Assessment: SU0259
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0259
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2007
Principal Product Wire and Tubing Processing Machines
NAICS 333519 - Rolling Mill and Other Metalworking Machinery Manufacturing
SIC 3549 - Metalworking Machinery, Nec
Sales $5,000,000-$10,000,000
# of Employees 46
Plant Area (Sq.Ft.) 26,856
Annual Production 3,000,000 Pounds
Production Hrs. Annual 2,040
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $38,247 331,533 kWh $0.12
Electricity Demand $15,532 1,616 kW-months/year $9.61
Electricity Fees $4,819 - $ -
Natural Gas $10,285 756 MMBtu $13.60
TOTAL ENERGY COSTS $68,883
RECOMMENDED SAVINGS* $5,788 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $3,537
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Personnel Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$1,279
Cost:
-
$856 7,446 $423 44 - - - - $856
7,446
kWh
$423
44
kW-months/year
-
-
$
-
-
$
02: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$1,332
Cost:
-
- - - - - - $1,332 - -
-
kWh
-
-
kW-months/year
-
-
$
$1,332
-
$
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$411
Cost:
-
- - - - - - $411 - -
-
kWh
-
-
kW-months/year
-
-
$
$411
-
$
04: 2.7229 AIR CONDITION ONLY SPACE NECESSARY Savings:
$763
Cost:
$13
$600 5,214 $163 17 - - - - $600
5,214
kWh
$163
17
kW-months/year
-
-
$
-
-
$
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$290
Cost:
$38
$175 1,520 $115 12 - - - - $175
1,520
kWh
$115
12
kW-months/year
-
-
$
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$221
Cost:
$50
$148 1,285 $73 8 - - - - $148
1,285
kWh
$73
8
kW-months/year
-
-
$
-
-
$
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$410
Cost:
$232
$275 2,387 $135 14 - - - - $275
2,387
kWh
$135
14
kW-months/year
-
-
$
-
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$272
Cost:
$231
$161 1,402 $19 2 $92 - - - $161
1,402
kWh
$19
2
kW-months/year
$92
-
$
-
-
$
09: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES Savings:
$508
Cost:
$546
$508 4,418 - - - - - - $508
4,418
kWh
-
-
kW-months/year
-
-
$
-
-
$
10: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$302
Cost:
$973
$302 2,627 - - - - - - $302
2,627
kWh
-
-
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$5,788
Cost:
$2,083
$3,025 26,299 $928 97 $92 - $1,743 - $3,025
26,299
kWh
$928
97
kW-months/year
$92
-
$
$1,743
-
$
TOTAL IMPLEMENTED Savings:
$3,537
Cost:
$1,537
$2,517 21,881 $928 97 $92 - - - $2,517
21,881
kWh
$928
97
kW-months/year
$92
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Personnel Changes One-time Revenue or Avoided Cost