IAC Assessment: SU0287
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0287
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2010
Principal Product Sheet Metal Fabrication and Assembly
NAICS 333514 - Special Die and Tool, Die Set, Jig, and Fixture Manufacturing
SIC 3544 - Special Dies, Tools, Jigs & Fixtures
Sales $10,000,000-$50,000,000
# of Employees 131
Plant Area (Sq.Ft.) 165,000
Annual Production 1,421,000 Pounds
Production Hrs. Annual 6,240
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $182,181 3,243,500 kWh $0.06
Electricity Demand $73,083 7,130 kW-months/year $10.25
Electricity Fees $27,943 - $ -
Natural Gas $24,824 2,023 MMBtu $12.27
TOTAL ENERGY COSTS $308,031
RECOMMENDED SAVINGS* $71,978 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $21,742
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Administrative Changes Electricity Usage Electricity Demand Electricity Fees Administrative Changes
$ kWh $ kW-months/year $ $ $ $
01: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES Savings:
$7,962
Cost:
-
- - - - $7,962 - - - -
-
kWh
-
-
kW-months/year
$7,962
-
$
-
-
$
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$4,424
Cost:
-
$3,532 63,072 $892 87 - - - - $3,532
63,072
kWh
$892
87
kW-months/year
-
-
$
-
-
$
03: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$3,705
Cost:
-
$3,705 66,155 - - - - - - $3,705
66,155
kWh
-
-
kW-months/year
-
-
$
-
-
$
04: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES Savings:
$1,358
Cost:
-
$681 12,155 $677 66 - - - - $681
12,155
kWh
$677
66
kW-months/year
-
-
$
-
-
$
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,950
Cost:
$338
$2,355 42,048 $595 58 - - - - $2,355
42,048
kWh
$595
58
kW-months/year
-
-
$
-
-
$
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,701
Cost:
$1,174
$2,158 38,544 $543 53 - - - - $2,158
38,544
kWh
$543
53
kW-months/year
-
-
$
-
-
$
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$162
Cost:
$77
$162 2,901 - - - - - - $162
2,901
kWh
-
-
kW-months/year
-
-
$
-
-
$
08: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$48,463
Cost:
$70,000
- - - - - - $48,463 - -
-
kWh
-
-
kW-months/year
-
-
$
$48,463
-
$
09: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES Savings:
$253
Cost:
$641
$253 4,525 - - - - - - $253
4,525
kWh
-
-
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$71,978
Cost:
$72,230
$12,846 229,400 $2,707 264 $7,962 - $48,463 - $12,846
229,400
kWh
$2,707
264
kW-months/year
$7,962
-
$
$48,463
-
$
TOTAL IMPLEMENTED Savings:
$21,742
Cost:
$1,512
$11,750 209,819 $2,030 198 $7,962 - - - $11,750
209,819
kWh
$2,030
198
kW-months/year
$7,962
-
$
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Electricity Fees Administrative Changes Electricity Usage Electricity Demand Electricity Fees Administrative Changes