Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2013 |
Principal Product | Bulk Organic Milk |
NAICS | 311511 - Fluid Milk Manufacturing |
SIC | 2026 - Fluid Milk |
Sales | $500,000-$1,000,000 |
# of Employees | 5 |
Plant Area (Sq.Ft.) | 26,260 |
Annual Production | 2,100,000 Pounds |
Production Hrs. Annual | 2,912 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,005 | 13,599 | kWh | $0.07 |
Electricity Fees | $396 | - | $ | - |
LPG | $1,608 | 63 | MMBtu | $25.52 |
TOTAL ENERGY COSTS | $3,009 | |||
RECOMMENDED SAVINGS* | $739 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $281 |
#|Description |
Savings Cost |
Status | Electricity Usage | LPG | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | LPG | Personnel Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $31 Cost: - |
$31 | 421 | - | - | - | - | - | - |
$31 421 kWh |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.9112 USE SOLAR HEAT TO HEAT WATER |
Savings: $458 Cost: $10,804 |
- | - | $458 | 18 | - | - | - | - |
- - kWh |
$458 18 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $250 Cost: $12,804 |
$148 | 1,867 | - | - | $22 | - | $80 | - |
$148 1,867 kWh |
- - MMBtu |
$22 - $ |
$80 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $739 Cost: $23,608 |
$179 | 2,288 | $458 | 18 | $22 | - | $80 | - | $179 2,288 kWh |
$458 18 MMBtu |
$22 - $ |
$80 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $281 Cost: $12,804 |
$179 | 2,288 | - | - | $22 | - | $80 | - | $179 2,288 kWh |
- - MMBtu |
$22 - $ |
$80 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | LPG | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | LPG | Personnel Changes | One-time Revenue or Avoided Cost |