Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2013 |
Principal Product | Digital Imaging Papers and Specialty Papers |
NAICS | 322299 - All Other Converted Paper Product Manufacturing |
SIC | 2672 - Paper Coated And Laminated, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 143 |
Plant Area (Sq.Ft.) | 400,000 |
Annual Production | 6,500,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $357,527 | 5,917,416 | kWh | $0.06 |
Electricity Demand | $62,529 | 13,815 | kW-months/year | $4.53 |
Electricity Fees | $478 | - | $ | - |
Natural Gas | $67,913 | 8,718 | MMBtu | $7.79 |
TOTAL ENERGY COSTS | $496,347 | |||
RECOMMENDED SAVINGS* | $14,704 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $7,665 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $85 Cost: - |
$58 | 960 | $27 | 6 | - | - | - | - | - | - | - | - |
$58 960 kWh |
$27 6 kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,848 Cost: $517 |
$1,848 | 30,801 | - | - | - | - | - | - | - | - | - | - |
$1,848 30,801 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,655 Cost: $2,760 |
$4,655 | 77,584 | - | - | - | - | - | - | - | - | - | - |
$4,655 77,584 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $469 Cost: $346 |
$158 | 2,628 | $18 | 4 | - | - | - | - | $123 | - | $170 | - |
$158 2,628 kWh |
$18 4 kW-months/year |
- - $ |
- - MMBtu |
$123 - $ |
$170 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $693 Cost: $895 |
- | - | - | - | - | - | $693 | 89 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$693 89 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES |
Savings: $290 Cost: $596 |
$290 | 4,837 | - | - | - | - | - | - | - | - | - | - |
$290 4,837 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $6,664 Cost: $33,352 |
- | - | - | - | $6,664 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$6,664 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $14,704 Cost: $38,466 |
$7,009 | 116,810 | $45 | 10 | $6,664 | - | $693 | 89 | $123 | - | $170 | - | $7,009 116,810 kWh |
$45 10 kW-months/year |
$6,664 - $ |
$693 89 MMBtu |
$123 - $ |
$170 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $7,665 Cost: $4,518 |
$6,661 | 111,013 | $18 | 4 | - | - | $693 | 89 | $123 | - | $170 | - | $6,661 111,013 kWh |
$18 4 kW-months/year |
- - $ |
$693 89 MMBtu |
$123 - $ |
$170 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | One-time Revenue or Avoided Cost |