Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2013 |
Principal Product | Automotive Tires |
NAICS | 326211 - Tire Manufacturing (except Retreading) |
SIC | 3011 - Tires And Inner Tubes |
Sales | >$500,000,000 |
# of Employees | 1,323 |
Plant Area (Sq.Ft.) | 2,000,000 |
Annual Production | 3,500,000 Pieces |
Production Hrs. Annual | 8,280 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $4,483,736 | 89,674,716 | kWh | $0.05 |
Electricity Demand | $1,268,784 | 158,598 | kW-months/year | $8.00 |
Electricity Fees | $166,153 | - | $ | - |
Natural Gas | $2,981,865 | 581,871 | MMBtu | $5.12 |
TOTAL ENERGY COSTS | $8,900,538 | |||
RECOMMENDED SAVINGS* | $41,064 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $31,456 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $24,796 Cost: - |
$8,684 | 173,672 | $16,112 | 2,014 | - | - | - | - |
$8,684 173,672 kWh |
$16,112 2,014 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $119 Cost: - |
$119 | 2,384 | - | - | - | - | - | - |
$119 2,384 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $9,608 Cost: $780 |
$6,251 | 125,028 | $1,448 | 181 | $1,495 | - | $414 | - |
$6,251 125,028 kWh |
$1,448 181 kW-months/year |
$1,495 - $ |
$414 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $304 Cost: $1,295 |
$248 | 4,968 | $56 | 7 | - | - | - | - |
$248 4,968 kWh |
$56 7 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7122 DISCONNECT BALLASTS |
Savings: $4,434 Cost: $21,152 |
$3,602 | 72,036 | $832 | 104 | - | - | - | - |
$3,602 72,036 kWh |
$832 104 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,803 Cost: $8,868 |
$869 | 17,388 | $200 | 25 | $390 | - | $344 | - |
$869 17,388 kWh |
$200 25 kW-months/year |
$390 - $ |
$344 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $41,064 Cost: $32,095 |
$19,773 | 395,476 | $18,648 | 2,331 | $1,885 | - | $758 | - | $19,773 395,476 kWh |
$18,648 2,331 kW-months/year |
$1,885 - $ |
$758 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $31,456 Cost: $31,315 |
$13,522 | 270,448 | $17,200 | 2,150 | $390 | - | $344 | - | $13,522 270,448 kWh |
$17,200 2,150 kW-months/year |
$390 - $ |
$344 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Personnel Changes | One-time Revenue or Avoided Cost |