Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2015 |
Principal Product | Super Alloy Metals |
NAICS | 331492 - Secondary Smelting, Refining, and Alloying of Nonferrous Metal (except Copper and Aluminum) |
SIC | 3399 - Primary Metal Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 130,000 |
Annual Production | 2,000,000 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $283,209 | 5,604,337 | kWh | $0.05 |
Electricity Demand | $80,997 | 23,525 | kW-months/year | $3.44 |
Natural Gas | $49,113 | 6,458 | MMBtu | $7.60 |
TOTAL ENERGY COSTS | $2,080,055 | |||
RECOMMENDED SAVINGS* | $1,297,002 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $8,487 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Gaseous Waste | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | Gaseous Waste | Personnel Changes | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $854 Cost: $514 |
$210 | 4,118 | $19 | 6 | - | - | - | - | $475 | - | $150 | - |
$210 4,118 kWh |
$19 6 kW-months/year |
- - $ |
- - lb |
$475 - $ |
$150 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $1,281,641 Cost: $1,000,000 |
$(-134,028) | (-2,628,000) | $(-12,384) | (-3,600) | - | - | $1,428,053 | 45,464 | - | - | - | - |
$(-134,028) (-2,628,000) kWh |
$(-12,384) (-3,600) kW-months/year |
- - $ |
$1,428,053 45,464 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.1161 ELIMINATE/REDUCE AN OPERATION |
Savings: $4,112 Cost: $3,576 |
$(-99) | (-1,950) | $(-124) | (-36) | - | - | - | - | $1,900 | - | $2,435 | - |
$(-99) (-1,950) kWh |
$(-124) (-36) kW-months/year |
- - $ |
- - lb |
$1,900 - $ |
$2,435 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $1,129 Cost: $998 |
$1,129 | 22,147 | - | - | - | - | - | - | - | - | - | - |
$1,129 22,147 kWh |
- - kW-months/year |
- - $ |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,883 Cost: $2,400 |
$1,883 | 36,912 | - | - | - | - | - | - | - | - | - | - |
$1,883 36,912 kWh |
- - kW-months/year |
- - $ |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $5,745 Cost: $12,259 |
- | - | - | - | $5,745 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$5,745 - $ |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,638 Cost: $5,256 |
$1,050 | 20,586 | $194 | 56 | - | - | - | - | $114 | - | $280 | - |
$1,050 20,586 kWh |
$194 56 kW-months/year |
- - $ |
- - lb |
$114 - $ |
$280 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $1,297,002 Cost: $1,025,003 |
$(-129,855) | (-2,546,187) | $(-12,295) | (-3,574) | $5,745 | - | $1,428,053 | 45,464 | $2,489 | - | $2,865 | - | $(-129,855) (-2,546,187) kWh |
$(-12,295) (-3,574) kW-months/year |
$5,745 - $ |
$1,428,053 45,464 lb |
$2,489 - $ |
$2,865 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $8,487 Cost: $11,746 |
$3,044 | 59,666 | $89 | 26 | - | - | - | - | $2,489 | - | $2,865 | - | $3,044 59,666 kWh |
$89 26 kW-months/year |
- - $ |
- - lb |
$2,489 - $ |
$2,865 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Gaseous Waste | Personnel Changes | One-time Revenue or Avoided Cost | Electricity Usage | Electricity Demand | Electricity Fees | Gaseous Waste | Personnel Changes | One-time Revenue or Avoided Cost |