Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Syracuse University |
---|---|
Assessment Year | 2015 |
Principal Product | Printed and Electronic Communication Programs |
NAICS | 323111 - Commercial Printing (except Screen and Books) |
SIC | 2752 - Commercial Printing, Lithographic |
Sales | $10,000,000-$50,000,000 |
# of Employees | 65 |
Plant Area (Sq.Ft.) | 56,000 |
Annual Production | 100,000,000 Pieces |
Production Hrs. Annual | 4,680 |
Location (State) | NY |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $192,886 | 2,078,820 | kWh | $0.09 |
Natural Gas | $4,049 | 639 | MMBtu | $6.34 |
Other Energy | $36,859 | 3,107 | MMBtu | $11.86 |
TOTAL ENERGY COSTS | $233,794 | |||
RECOMMENDED SAVINGS* | $11,356 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Other Energy | One-time Revenue or Avoided Cost | Electricity Usage | Natural Gas | Other Energy | One-time Revenue or Avoided Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4322 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES |
Savings: $837 Cost: - |
$837 | 9,000 | - | - | - | - | - | - |
$837 9,000 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $218 Cost: $67 |
$218 | 2,340 | - | - | - | - | - | - |
$218 2,340 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $484 Cost: $529 |
$244 | 2,628 | - | - | - | - | $240 | - |
$244 2,628 kWh |
- - MMBtu |
- - MMBtu |
$240 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $1,131 Cost: $4,339 |
$1,131 | 12,168 | - | - | - | - | - | - |
$1,131 12,168 kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2628 UTILIZE A LESS EXPENSIVE COOLING METHOD |
Savings: $8,686 Cost: $33,817 |
- | - | $(-23,173) | (-3,655) | $36,859 | 3,107 | $(-5,000) | - |
- - kWh |
$(-23,173) (-3,655) MMBtu |
$36,859 3,107 MMBtu |
$(-5,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,356 Cost: $38,752 |
$2,430 | 26,136 | $(-23,173) | (-3,655) | $36,859 | 3,107 | $(-4,760) | - | $2,430 26,136 kWh |
$(-23,173) (-3,655) MMBtu |
$36,859 3,107 MMBtu |
$(-4,760) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - - kWh |
- - MMBtu |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Other Energy | One-time Revenue or Avoided Cost | Electricity Usage | Natural Gas | Other Energy | One-time Revenue or Avoided Cost |