IAC Assessment: SU0422
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SU0422
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Syracuse University
Assessment Year 2016
Principal Product Specialty Metal Products
NAICS 332710 - Machine Shops
SIC 3599 - Industrial Machinery, Nec
Sales $5,000,000-$10,000,000
# of Employees 56
Plant Area (Sq.Ft.) 38,000
Annual Production 623,000 Pieces
Production Hrs. Annual 2,040
Location (State) NY
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $65,128 1,217,840 kWh $0.05
Electricity Demand $30,122 2,837 kW-months/year $10.62
Electricity Fees $3,648 - $ -
Natural Gas $4,730 855 MMBtu $5.53
TOTAL ENERGY COSTS $103,628
RECOMMENDED SAVINGS* $18,321 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $16,145
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 3.1161 ELIMINATE/REDUCE AN OPERATION Savings:
$1,752
Cost:
-
$966 18,060 $786 74 - - - - - - $966
18,060
kWh
$786
74
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$450
Cost:
-
$450 8,405 - - - - - - - - $450
8,405
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$484
Cost:
$164
$141 2,637 $38 4 - - $235 - $70 - $141
2,637
kWh
$38
4
kW-months/year
-
-
MMBtu
$235
-
$
$70
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$153
Cost:
$150
$153 2,856 - - - - - - - - $153
2,856
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
05: 3.1161 ELIMINATE/REDUCE AN OPERATION Savings:
$880
Cost:
$960
$(-10) (-188) $(-115) (-11) - - $417 - $588 - $(-10)
(-188)
kWh
$(-115)
(-11)
kW-months/year
-
-
MMBtu
$417
-
$
$588
-
$
06: 2.7314 REDUCE VENTILATION AIR Savings:
$846
Cost:
$880
$200 3,736 - - $646 135 - - - - $200
3,736
kWh
-
-
kW-months/year
$646
135
MMBtu
-
-
$
-
-
$
07: 2.6211 CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES Savings:
$189
Cost:
$332
$189 3,534 - - - - - - - - $189
3,534
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$13,567
Cost:
$25,530
$6,213 116,137 $7,251 683 - - $1,379 - $(-1,276) - $6,213
116,137
kWh
$7,251
683
kW-months/year
-
-
MMBtu
$1,379
-
$
$(-1,276)
-
$
TOTAL RECOMMENDED Savings:
$18,321
Cost:
$28,016
$8,302 155,177 $7,960 750 $646 135 $2,031 - $(-618) - $8,302
155,177
kWh
$7,960
750
kW-months/year
$646
135
MMBtu
$2,031
-
$
$(-618)
-
$
TOTAL IMPLEMENTED Savings:
$16,145
Cost:
$26,176
$7,662 143,224 $8,075 760 - - $1,614 - $(-1,206) - $7,662
143,224
kWh
$8,075
760
kW-months/year
-
-
MMBtu
$1,614
-
$
$(-1,206)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes One-time Revenue or Avoided Cost