Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Texas, Arlington |
---|---|
Assessment Year | 2001 |
Principal Product | PVC Core Foam |
NAICS | n/a |
SIC | 3086 - Plastics Foam Products |
Sales | $10,000,000-$50,000,000 |
# of Employees | 150 |
Plant Area (Sq.Ft.) | 80,000 |
Annual Production | 1,670 Tons |
Production Hrs. Annual | 8,328 |
Location (State) | TX |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $197,907 | 5,733,540 | kWh | $0.03 |
Electricity Demand | $86,959 | 10,624 | kW-months/year | $8.19 |
Electricity Fees | $2,578 | - | $ | - |
Natural Gas | $48,213 | 50,944 | MMBtu | $0.95 |
TOTAL ENERGY COSTS | $335,657 | |||
RECOMMENDED SAVINGS* | $23,447 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $20,985 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $8,063 Cost: $1,741 |
- | - | - | - | $8,063 | 1,772 |
- - kWh |
- - kW-months/year |
$8,063 1,772 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $5,666 Cost: $2,886 |
- | - | - | - | $5,666 | 1,244 |
- - kWh |
- - kW-months/year |
$5,666 1,244 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,918 Cost: - |
$3,918 | 117,261 | - | - | - | - |
$3,918 117,261 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4314 USE SYNTHETIC LUBRICANT |
Savings: $2,175 Cost: - |
$1,269 | 37,987 | $906 | 73 | - | - |
$1,269 37,987 kWh |
$906 73 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6215 SHUT OFF AIR CONDITIONING IN WINTER HEATING SEASON |
Savings: $2,036 Cost: - |
- | - | - | - | $2,036 | 447 |
- - kWh |
- - kW-months/year |
$2,036 447 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7132 INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS |
Savings: $999 Cost: $46 |
$495 | 14,840 | $504 | 41 | - | - |
$495 14,840 kWh |
$504 41 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $303 Cost: $313 |
$303 | 9,069 | - | - | - | - |
$303 9,069 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2523 REDUCE INFILTRATION TO REFRIGERATED AREAS; ISOLATE HOT EQUIPMENT FROM REFRIGERATED AREAS |
Savings: $287 Cost: $23 |
- | - | - | - | $287 | 63 |
- - kWh |
- - kW-months/year |
$287 63 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $23,447 Cost: $5,009 |
$5,985 | 179,157 | $1,410 | 114 | $16,052 | 3,526 | $5,985 179,157 kWh |
$1,410 114 kW-months/year |
$16,052 3,526 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $20,985 Cost: $4,986 |
$4,716 | 141,170 | $504 | 41 | $15,765 | 3,463 | $4,716 141,170 kWh |
$504 41 kW-months/year |
$15,765 3,463 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |