IAC Assessment: TA0090
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Texas, Arlington
Assessment Year 2004
Principal Product Saw Cut Lumber and Crates
NAICS 321113 - Sawmills
SIC 2421 - Sawmills And Planing Mills, General
Sales $50,000,000-$100,000,000
# of Employees 100
Plant Area (Sq.Ft.) 23,000
Annual Production 63,000 Thousand Feet
Production Hrs. Annual 2,379
Location (State) TX
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $46,943 620,480 kWh $0.08
Electricity Demand $8,277 4,244 kW-months/year $1.95
Electricity Fees $300 - $ -
TOTAL ENERGY COSTS $57,440
RECOMMENDED SAVINGS* $163,080 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $280
#|Description Savings
Cost
Status Electricity Usage Solid Waste (non-haz) Personnel Changes Primary Product By-product Production Electricity Usage Solid Waste (non-haz) Personnel Changes Primary Product By-product Production
$ kWh $ lb $ $ $ $ $ $
01: 4.512 CONDENSE OPERATION INTO ONE BUILDING Savings:
$91,320
Cost:
$20,000
- - - - $31,320 - $60,000 - - - -
-
kWh
-
-
lb
$31,320
-
$
$60,000
-
$
-
-
$
02: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$42,810
Cost:
$64,000
- - - - $42,810 - - - - - -
-
kWh
-
-
lb
$42,810
-
$
-
-
$
-
-
$
03: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES Savings:
$23,490
Cost:
$45,000
- - - - $23,490 - - - - - -
-
kWh
-
-
lb
$23,490
-
$
-
-
$
-
-
$
04: 4.212 ADOPT IN-HOUSE MATERIAL GENERATION Savings:
$2,350
Cost:
-
- - - - - - - - $2,350 - -
-
kWh
-
-
lb
-
-
$
-
-
$
$2,350
-
$
05: 3.5212 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS Savings:
$1,920
Cost:
$120
- - $1,920 5,000 - - - - - - -
-
kWh
$1,920
5,000
lb
-
-
$
-
-
$
-
-
$
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$910
Cost:
$8
$910 10,872 - - - - - - - - $910
10,872
kWh
-
-
lb
-
-
$
-
-
$
-
-
$
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$280
Cost:
$120
$280 3,367 - - - - - - - - $280
3,367
kWh
-
-
lb
-
-
$
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$163,080
Cost:
$129,248
$1,190 14,239 $1,920 5,000 $97,620 - $60,000 - $2,350 - $1,190
14,239
kWh
$1,920
5,000
lb
$97,620
-
$
$60,000
-
$
$2,350
-
$
TOTAL IMPLEMENTED Savings:
$280
Cost:
$120
$280 3,367 - - - - - - - - $280
3,367
kWh
-
-
lb
-
-
$
-
-
$
-
-
$
Savings
Cost
$ kWh $ lb $ $ $ $ $ $
Electricity Usage Solid Waste (non-haz) Personnel Changes Primary Product By-product Production Electricity Usage Solid Waste (non-haz) Personnel Changes Primary Product By-product Production