Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Tennessee |
---|---|
Assessment Year | 1982 |
Principal Product | ELECTRONIC COILS |
NAICS | n/a |
SIC | 3677 - Electronic Coils And Transformers |
Sales | $1,000,000-$5,000,000 |
# of Employees | 71 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,000,000 Pieces |
Production Hrs. Annual | 2,340 |
Location (State) | TN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $24,796 | 444,314 | kWh | $0.06 |
Fuel Oil #2 | $7,055 | 837 | MMBtu | $8.43 |
TOTAL ENERGY COSTS | $31,851 | |||
RECOMMENDED SAVINGS* | $4,168 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $844 Cost: $25 |
$844 | 28,136 | - | - | - | - |
$844 28,136 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1332 CONVERT COMBUSTION EQUIPMENT TO BURN NATURAL GAS |
Savings: $2,418 Cost: $3,500 |
- | - | $(-1,940) | (-485) | $4,358 | 517 |
- - kWh |
$(-1,940) (-485) MMBtu |
$4,358 517 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $642 Cost: $2,100 |
$642 | 21,395 | - | - | - | - |
$642 21,395 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $264 Cost: - |
$264 | 8,792 | - | - | - | - |
$264 8,792 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $4,168 Cost: $5,625 |
$1,750 | 58,323 | $(-1,940) | (-485) | $4,358 | 517 | $1,750 58,323 kWh |
$(-1,940) (-485) MMBtu |
$4,358 517 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - - kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Fuel Oil #2 | Electricity Usage | Natural Gas | Fuel Oil #2 |